Two Ways to Face the Unknown

In one line A predictive approach plans the whole job first; an adaptive one plans a little, builds, learns and plans again.

There are two broad ways to begin a project whose end you cannot yet see. The first, often called predictive or plan-driven, works out the whole job before the main work starts: what will be made, in what order, at what cost. Changes are allowed, but they go through a process, because each one disturbs a plan that many people rely on. The second, called adaptive or iterative, plans only the next short stretch in detail. The team builds a small piece, shows it to the people who will use it, learns from them, and plans again.

Neither idea is new. Builders have drawn full plans before laying foundations for centuries, and a team of programmers in Los Angeles was already building software in increments in 1957. Earlier in the course, When a Full Plan First Fits set out the signs that favour planning in full, and What Agile Was Reacting Against showed what pushed many software teams the other way.

The useful question is not which approach is more modern but how much is known at the start. A hospital extension has rooms whose sizes, gas lines and fire exits are set by rules and by long experience of how wards work. Much is known, and a change after the concrete is poured costs dearly. A new online booking service for the same hospital is different: nobody yet knows how patients will use it, which screens will confuse them, or what the clinics will ask for once they see it. There a detailed plan would mostly record guesses.

So each approach is a response to a kind of unknown. Planning first suits what can be found out by thinking and is costly to change; learning first suits what can only be found out by trying. Most projects hold some of each, which is why the hardest arguments this week are about the mix.

Two projects, one hospital

Illustration: Two projects, one hospital

Adnan runs the estates office of a teaching hospital in Irbid, Jordan, and this year he has two projects. The first is a four-storey extension for a new maternity unit. Its drawings are finished and approved by the fire inspectors, the steel is ordered, and any change now goes to a weekly review where the architect, the engineer and the head midwife weigh its cost before anyone says yes.

The second is an online service that lets patients book clinic appointments on their phones. Here Adnan does the opposite. A small team builds the first screens in a fortnight and watches twenty patients try them in the waiting room. Half cannot find the clinic they want, so the team changes the menus and tries again. Colleagues ask why he is strict with one project and loose with the other. He answers that he knows how a maternity ward works, but not yet how his patients use a phone.

Try this today Pick one piece of work you have on now and ask: how much of what it needs do we truly know today?

Question 1 of 2

A city council in Cebu, Philippines, will rebuild a sea wall to a design checked by engineers. It will also start a text-message service warning residents of high tides, something nobody there has tried before.

Which way of working suits each part best?

Question 2 of 2

Two project leads in Nairobi are arguing. One says planning first is old-fashioned; the other says learning first is a passing fad.

According to the lesson, what should settle the choice between the two approaches?

Cite or share this lesson

A plain reference you can paste into notes or an essay:

Quest2Plan. “Two Ways to Face the Unknown.” https://quest2plan.com/learn/lesson/two-ways-to-face-the-unknown. Accessed 29 November 2026.

Sources
  • Iterative and incremental development — The history of building in increments, from a 1957 team in Los Angeles to the Space Shuttle's flight software.
  • Waterfall model — The plan-driven sequence of phases, its origins, and the arguments for and against it.