Too Many Projects
In one line Start more projects than you have people for and everything slows; leaders at the top have to limit what runs at once.
When an organization starts more projects than it has people for, each person is spread across several, each project waits for people who are busy elsewhere, and everything takes longer. Week 30 showed this for a team's tasks: with the same rate of finishing, more work in progress means a longer wait for each piece, as Little's Law put it in arithmetic. The same holds for whole projects. Ten projects that each get a tenth of a team's attention will finish much later than if the team took them a few at a time, and The Cost of Switching adds the hours lost moving between them.
Leaders start too many for understandable reasons. Each project has a champion, saying no feels like letting someone down, and starting looks like progress while finishing is slow. Lists of approved projects are rarely set against the people who must do them. And a project marked 'on hold' often still takes meetings and attention.
The cure has to come from the top, since a team cannot refuse work its leaders have approved. Leaders can count what is truly in progress, compare it with the people available, and set a limit: a new project waits until another finishes or is stopped. Some publish one ranked list, so a clash between two projects is settled by order, not by who argues loudest. Earlier, Saying No Before Saying Yes showed how to say no or not yet with care. From the top, a no also has to stick: no projects started by the back door, none funded from a spare budget.
A limit is a judgement, not a magic number. A project waiting on an outside approval can leave people idle, so a little parallel work is healthy, and some leaders worry that a strict limit will slow urgent work. The aim is enough in progress to keep people busy, and few enough that things finish.
A school with too much under way

Kamila becomes head of a secondary school in Samarkand, Uzbekistan, and finds fourteen improvement projects under way: a new reading scheme, a science club, a timetable change, a website, a parents' council and nine more. Most teachers sit on four or five project groups. Each group meets once a month, if enough people can come, and in the past year not one project has finished.
Kamila puts all fourteen on a single sheet and asks the staff to rank them. The top four continue; the rest are paused, each with a date when it will be looked at again, and the teachers on them move to the four. She tells the district office, which had asked for two of the paused ones, what the school is doing and why. By the summer the reading scheme and the timetable change are finished, and two paused projects have started in their place.
Try this today Count the projects you are part of this month. If you dropped to half, which would you keep, and what would finish sooner?
Cite or share this lesson
A plain reference you can paste into notes or an essay:
Quest2Plan. “Too Many Projects.” https://quest2plan.com/learn/lesson/too-many-projects. Accessed 29 November 2026.
Sources
- Little's law — The rule linking work in progress, rate of arrival and time spent in a system, and John Little's 1961 proof.
- Work in process — Partly finished work, its costs, and why lean thinking prefers less of it.