Those Who Do the Work Estimate It
In one line The people who will do the work usually estimate it better, and believe the number more, than anyone else.
Who should say how long a piece of work will take? In many organizations the answer has been the manager, the planner or the client, and the people who will do the work are handed a date. It looks efficient. It usually produces worse estimates, and estimates that nobody doing the work believes.
The doers know things the planner does not: that this machine needs an hour to warm up, that samples from one clinic always arrive mislabelled, that the last job like this needed a part made by hand. An estimate made without them leaves those things out. Being asked also changes how people treat the number. A date they worked out is a forecast they want to prove right; a date handed down is someone else's wish, and missing it feels like someone else's problem. The history here is long. When followers of Frederick Taylor timed workers with stopwatches in the early twentieth century to set the pace of their work, trade unions saw time study as a disguised way to speed people up, and opposed it.
Doers are not perfect estimators. Earlier in the course, The Planning Fallacy showed that people are most hopeful about their own tasks, and studies have found that outside observers err the other way, guessing too long. So the doers' figure is the starting point, checked against how their past jobs went.
What should a lead do when the team's number seems too high? Not overrule it. Ask what it includes and what drives it, and share anything the team may not know, such as a part already in stock. If the lead still thinks it is high, they can say why, and the team decides. A number the team has been argued out of is no longer its estimate.
Cedar screens for a hotel

Rashid runs a workshop in Fez, Morocco, that makes carved cedar doors and screens. A hotel orders forty screens and asks when they will be ready. Rashid has carved screens for thirty years, and his instinct says five weeks. This time, before answering, he asks the four carvers who will make them.
They say eight weeks. Rashid is tempted to tell them they are slow. Instead he asks why. The hotel's design has a deeper pattern than their usual work, which means different chisels and slower cuts, and the cedar in the yard is not yet dry enough for fine carving. Rashid had pictured the old pattern. He tells them a dealer can bring seasoned cedar by Monday, and the carvers rework their figure and settle on seven weeks. They finish in seven and a half, and nobody spends the last fortnight blaming the boss's date.
Try this today Next time you hand someone a task, ask them how long it will take before you mention any date you had in mind.
Cite or share this lesson
A plain reference you can paste into notes or an essay:
Quest2Plan. “Those Who Do the Work Estimate It.” https://quest2plan.com/learn/lesson/those-who-do-estimate. Accessed 29 November 2026.
Sources
- Time and motion study — Taylor's time study, how standards were set by observers, and why trade unions opposed it.
- Planning fallacy — Why people are hopeful about their own tasks, and why outside observers tend to guess too long.