The V

In one line The V writes each test when its matching design is written, which is why high-stakes, regulated fields favour it.

A requirement nobody can test is only a hope. The V-model, drawn earlier in the course in Seeing the Whole, pairs each level of design on its left side with a level of testing on its right: what users need with acceptance tests, the whole system's design with system tests, the architecture with integration tests, each module's design with unit tests. The part people forget is timing. Each test plan is written when its design is written, not after the building.

Writing the test early exposes vague design. 'The train stops before a red signal' sounds complete until someone writes the test and asks at what speed, on what slope, on wet rails or dry. Each requirement is traced to the parts that meet it and the tests that check it. The model grew up in the late 1980s, separately in Germany, for the defence ministry, and in the United States.

Fields where a fault can kill, and a regulator must approve the work, hold on to it. The international standard for medical device software, IEC 62304, first published in 2006, sorts software into three classes by the harm it could do, the highest for software that could contribute to death or serious injury, and asks more of the higher classes. Its activities run from requirements through design to unit, integration and system testing, much like the V, though it insists on no single model. The European standard for railway software, EN 50128, sets out a life cycle that is commonly drawn as a V, in the same spirit. Regulators want evidence, and the V produces it as it goes.

Critics say the V gives false comfort and favours test scripts written in advance over exploring. Defenders reply that pairing design with test holds in any order. Where faults are cheap, its paperwork may cost more than it saves; where they are not, it may be the cheapest thing on the project.

Wet rails

Illustration: Wet rails

Ceren is writing the requirements for the software that controls braking on a new tram line in Izmir, Turkey. Her team's rule is that no requirement is finished until its acceptance test is written beside it. One line reads: the tram stops before any signal showing red.

Drafting the test, she has to name the conditions: a full tram, top speed, the steepest stretch of track, and rails wet after rain. The braking figures her team was given were for dry rails. She raises it that afternoon, and the design engineers lower the speed limit approaching two downhill signals. Months later the system tests pass first time on a wet morning, and the safety assessor, reading down the list of requirements, finds a test result beside each one.

Try this today Take one requirement from something you are planning and write how you would test it. Notice what the requirement failed to say.

Question 1 of 2

Engineers in Bandung, Indonesia, are designing a new ticket gate. One document sets out how the card reader, the barrier and the central computer exchange messages.

On the right side of the V, which tests should be planned alongside that document?

Question 2 of 2

A firm in Amman, Jordan, writes software for an insulin pump, which could give a dangerous overdose if the software failed.

Under the medical software standard in the lesson, what follows from this?