The Railway Through the Pass

In one line With the money fixed and mountains in the way, Zhan Tianyou bent the design rather than the budget.

In 1905 the Qing government decided to build a railway from Beijing to Zhangjiakou, beyond the mountains to the northwest, with Chinese money and Chinese engineers alone. The chief engineer was Zhan Tianyou, who had taken a degree at Yale in 1881. The line ran about 200 kilometres, and its hardest stretch was the Nankou pass, where the track had to climb the Guangou valley to Badaling, beneath the Great Wall.

The money was limited, so Zhan could not simply buy his way through. A gentler route round the mountains was considered and dropped as too costly. Instead, near Qinglongqiao station, the line climbs in a zigzag: a train runs up one leg, stops, and reverses up the next, gaining height in a short distance. That cut the summit tunnel at Badaling from about 1.8 kilometres to about 1.1. To dig it faster, his teams sank vertical shafts from the mountaintop and worked outward from their foot as well as in from both ends, so more crews could dig at once.

Work began in October 1905, and the line opened in 1909, early and for less than the estimate. The choices had costs too. Even with the zigzag, the grade near Qinglongqiao is about 3.3 per cent, so the pass needed heavy articulated locomotives, and trains through the zigzag move slowly. In the 1950s a second line was built through easier ground.

Zhan's story is about which of scope, time and cost a project can bend. His money was fixed and the mountains could not move, so he bent the design: he accepted a steep, slow climb to avoid a long tunnel and a costly detour, and spent his ingenuity where it bought the most time, at the tunnel faces. A cheaper line then meant a slower railway for decades, a trade later engineers chose to revisit.

A pipeline round the ridge

Illustration: A pipeline round the ridge

Aizirek is the engineer for a drinking-water pipeline to three villages above Naryn, Kyrgyzstan, paid for by a fixed grant that cannot grow. The survey shows that the shortest route crosses a ridge of hard rock. Blasting through it would take most of the money and most of the short summer building season.

Aizirek redrew the route. The pipe would follow the slope round the ridge, longer but in soft ground that local crews could dig by hand, with a small pumping station to lift water over the last rise. She split the trench into five stretches, each with its own crew starting the same week, instead of one crew working up from the bottom. The pipeline was finished before the first snow and inside the grant. Her report named the cost she had moved rather than removed: the pump would need power and repairs for as long as the villages used it.

Try this today Pick one fixed limit on your work. Sketch two ways to change the design instead of the limit, and note what each would cost later.

Question 1 of 2

Wayra leads a team building a mountain road near Cusco, Peru, on a fixed government grant. The direct route needs a long tunnel that would use most of the money.

Which move is closest to Zhan's at the Nankou pass?

Question 2 of 2

A road tunnel near Bergen, Norway, is behind schedule because it is being dug from one end only. Sigrun, the site manager, has money for extra crews but nowhere for them to work.

What did Zhan's tunnel teams do that would help her?

Cite or share this lesson

A plain reference you can paste into notes or an essay:

Quest2Plan. “The Railway Through the Pass.” https://quest2plan.com/learn/lesson/the-railway-through-the-pass. Accessed 29 November 2026.

Sources
  • Zhan Tianyou — His life, his Yale degree of 1881, the zigzag near Qinglongqiao and the shaft at the Badaling tunnel.
  • Beijing–Zhangjiakou Railway — The building of the line from 1905 to 1909: its sections, the Guangou valley, the Badaling tunnel and its cost.
  • Beijing–Baotou railway — The 3.3 per cent grade near Qinglongqiao, the slow zigzag and the bypass built in the 1950s.