The Project as the Organization

In one line When the project is the organization, its team gains focus and speed, and loses its home when the work ends.

At the far end from departments by skill, the project is the organization. People join a project, not a department, and work on it full time until it ends. The project lead holds the budget, picks the team and answers for the result, and there are few department heads to bargain with. Large construction and engineering firms often work like this: each big site has its own manager, engineers, buyers and accountants, and the head office is small.

The gains are focus and speed. Everyone on the project wants the same thing, decisions are made close to the work, and nobody is called away to another job. Urgent military programmes have often run this way. When the United States Navy wanted a missile it could launch from a submarine, it set up a Special Projects Office under Rear Admiral William Raborn whose only task was Polaris, and which reported straight to the navy's top officer and its civilian head, bypassing the usual bureaus; PERT and the Polaris Missile told how it planned.

The costs come at the edges. Each project builds its own small departments, so skills and equipment are duplicated. Specialists have no senior colleague in their own field to learn from. And when the project ends, the team scatters: some move to the next job, some are let go, and what they learned leaves with them unless someone keeps it. The researchers Rolf Lundin and Anders Söderholm argued in 1995 that most organization theory assumes organizations are permanent, and that temporary ones need a theory of their own, built around time, task, team and transition.

Supporters say only a dedicated team gets hard things done fast. Critics answer that an organization made of projects keeps forgetting what it knew, and leaves people anxious between jobs. Many firms keep a small permanent core of specialists who move from project to project.

The last two months in Doha

Illustration: The last two months in Doha

Jarrah manages a contractor's site building a new district hospital outside Doha, Qatar. All 140 people on the job report, through their foremen and engineers, to him: the firm's head office in Amman supplies payroll and little else. In three years the site has made its own decisions on everything from concrete suppliers to the night-shift rota, and the hospital is on schedule. Now it has two months left.

Jarrah notices two things. The drainage engineer has solved a problem with the hospital's sloping ground that the next job will face too, but nothing about it is written down. And three of his best young engineers are already looking for work, because nobody has told them where they will go next. He books a day for the drainage engineer to record her method with photographs, and he asks head office to move his core team of twelve, as a group, to the firm's next big site, a school campus in Muscat. The firm agrees to move eight of them.

Try this today Think of a team you know that will break up when its work ends, and name one thing it knows that should not leave with it.

Question 1 of 2

A firm in Antofagasta, Chile, builds solar farms. Each farm has a lead with its own budget, and the engineers, buyers and accountants on each site work there full time until it opens.

Which feature marks this firm out as projectized rather than a matrix?

Question 2 of 2

A contractor finishes an irrigation dam in Ethiopia and its team disperses. Five years later the firm wins a similar dam and repeats a costly mistake with the spillway that the first team had learned to avoid.

Which weakness of a projectized firm does this show?

Cite or share this lesson

A plain reference you can paste into notes or an essay:

Quest2Plan. “The Project as the Organization.” https://quest2plan.com/learn/lesson/the-project-as-the-organization. Accessed 29 November 2026.