The Last Ten Per Cent

In one line Work reaches ninety per cent quickly and then stalls, because the last tenth was never counted as real work.

Ask a team how far along it is, and the answer is often ninety per cent. Ask again a month later, and it is ninety-five. A month after that, it is still ninety-five. Tom Cargill of Bell Labs turned this into a joke that Jon Bentley printed in 1985: the first ninety per cent of the code takes the first ninety per cent of the time, and the last ten per cent takes the other ninety per cent. Builders, event planners and authors know the same pattern.

The cause is rarely laziness. The first part of most work is its visible bulk: walls going up, screens that look finished, chapters drafted. The last tenth is a different kind of work, and easy to forget when planning. Pieces built apart must be joined, and often do not fit. Testing turns up faults that need fixing. A builder's snagging list of small defects must be cleared, inspections need a booked date, and certificates, manuals and other paperwork must be written. Each item is small; together they are large, and many can only start when everything else is done, so they cannot be shared out across the team.

Per cent complete is also usually a guess, made by looking at what has been done rather than at what is left. Earlier in the course, Earned Value in Plain Words measured progress by work actually finished, and the same habit helps here.

Planning for the last tenth honestly takes three habits. Name the final stretch as real tasks, with estimates as careful as the first ones: joining, testing, fixing, inspection, handover, paperwork. Count only things that are wholly finished, so that nearly done never counts as done. And ask what is left, and how long each piece will take, rather than how far along people are. The last tenth will still be hard, but it will be in the plan.

Go deeper

Some teams measure progress with a strict rule: a task counts as zero until it is finished, and then as whole. It is crude, and it makes progress look slow in the early weeks, but it cannot report ninety per cent for months on end. A gentler version gives half credit when a task starts and the rest when it ends. Either way the point is the same: measure what is finished, not what has been touched.

Eleven weeks on one sheet

Illustration: Eleven weeks on one sheet

In May, the builder told Zafar that his family's new house on the edge of Tlemcen, in Algeria, was ninety per cent done. The walls were plastered, the roof was tiled and the windows were in. Zafar told his landlord they would leave in July and began packing.

July came and the house was still ninety per cent done. The water pipes had been laid before the kitchen plan changed, so the sink sat a metre from its outlet. The electrician could not finish until the plasterer patched the walls he had cut. The gas boiler needed an inspector's certificate, and the first free date was in August. Zafar sat down with the builder and wrote every remaining job on one sheet, each with its own estimate. It came to eleven weeks. The family moved in at the end of September, later than hoped, but on the date the sheet had given.

Try this today Take one job you call nearly done. Write every task still left, however small, with a time beside each, and add them up.

More on this trap: The ninety per cent syndrome →

Question 1 of 2

A software team in Bandung, Indonesia, has reported its new clinic-booking app as 90 per cent complete in six weekly reports in a row.

What is the most likely explanation for the stuck figure?

Question 2 of 2

A contractor's plan for refitting a school in Valparaíso, Chile, gives ten weeks to building work and one final day to 'tidy up, inspection and handover'.

Where is the plan weakest?

Cite or share this lesson

A plain reference you can paste into notes or an essay:

Quest2Plan. “The Last Ten Per Cent.” https://quest2plan.com/learn/lesson/the-last-ten-percent. Accessed 29 November 2026.

Sources
  • Ninety-ninety rule — Tom Cargill's rule about the last ten per cent of the work, published by Jon Bentley in 1985.
  • Punch list — The snag list of small faults that a builder must clear near the end of a job before final payment.