Starting at the Last Minute
In one line Work tends to start late and swell to fill the time it is given, so padded deadlines often finish later.
Give a student three weeks for an essay and a familiar thing happens: the first two weeks pass with good intentions, and the essay is written in the last few nights. Eliyahu Goldratt, in his 1997 business novel Critical Chain, called this student syndrome, and he meant it for adults as much as students. People start when the deadline feels close, because other jobs seem more urgent and a far-off date feels like plenty of room. The safety margin is spent waiting, so when a surprise comes there is no time left to absorb it.
A second habit works from the other end. In 1955 the British naval historian C. Northcote Parkinson wrote a satirical essay in The Economist that opened by calling it 'a commonplace observation that work expands so as to fill the time available for its completion.' Given more time, people rarely finish sooner. They polish, add steps, wait for others and hesitate, and the work swells to fit the space.
Put the two together and padding a deadline backfires. Earlier this week, The Planning Fallacy showed why estimates run short, and the usual answer is to add a safety week to each task. The person doing the task, knowing the cushion is there, starts later; the work fills what is left; and the safety week disappears without a trace. Tasks that finish early are rarely handed over early, while tasks that finish late pass their lateness on to the next.
The common fixes are to set each task's date close to an honest estimate, keep the safety margin as one shared buffer at the end, take the first small step of every task at once (above all anything that needs another person's reply), and make early hand-overs welcome. Extra time is not always wasted, though: hard thinking, delicate talks and creative work sometimes need room, and a near deadline can focus effort well.
The report with a reserve

Gabriela leads a team of four in the planning office of a water utility in Arequipa, Peru. Last year the team was given six weeks for an annual report that needed about three weeks of work. They finished on the last evening, with two sections thin and a chart missing, because figures from the finance office arrived late.
This year Gabriela tried another way. She asked each writer for an honest estimate with no padding, set their dates from those, and kept the rest of the time as a shared reserve that nobody could plan into. On the first morning she asked everyone to send their requests for figures to other offices before writing a word. The finance figures were late again, by eight days, but there was room to wait for them. The report went in four days early.
Try this today Pick a task due next week and do its first small step today, especially any part that needs someone else to reply.
Cite or share this lesson
A plain reference you can paste into notes or an essay:
Quest2Plan. “Starting at the Last Minute.” https://quest2plan.com/learn/lesson/the-last-minute. Accessed 29 November 2026.
Sources
- Parkinson's law — The 1955 essay in The Economist and the idea that work expands to fill the time available.
- Student syndrome — Starting work only as the deadline nears, as named by Eliyahu Goldratt.
- Critical chain project management — Goldratt's 1997 approach, which pools safety margins into shared buffers.