The Cost of Switching

In one line Every change of task costs time and attention, and people spread across many projects lose much of their week to it.

Every change of task has a price. Psychologists have studied this since Arthur Jersild's experiments in 1927. In the laboratory, people asked to alternate between two simple tasks, such as judging numbers and judging letters, are slower and make more mistakes just after a switch than when they repeat the same task. Joshua Rubinstein, David Meyer and Jeffrey Evans reported in 2001 that the cost grows with the complexity of the tasks, and is larger when switching to a less familiar one.

In one switch the loss is small, a fraction of a second in the simple tasks studied. In real work it adds up in other ways. Coming back to a report after a meeting means rereading, rebuilding the argument and recalling what you had decided. And people spread across several projects add a bigger cost that no laboratory measures: everyone who needs them waits, because each project gets them for only a slice of the week.

That waiting is where context switching meets the rest of this week. A person shared among four projects has four queues in front of them, and each queue's wait grows with the work in it. Earlier in the course, Stop Starting, Start Finishing gave the remedy for teams, and for people it is much the same: fewer things at once and longer stretches on each. That can mean fewer projects each, meeting-free blocks, questions gathered together, and asking what a new request replaces.

Some switching is healthy. A short change can refresh tired attention, someone blocked on one task can usefully pick up another, and roles such as a duty nurse or a help desk exist to answer interruptions. The aim is switches chosen rather than imposed, and the week's tools each fit a different problem: a board for unseen work, limits for too much started, the five steps for one slow step, and cost of delay for what goes first.

Five projects, one adviser

Illustration: Five projects, one adviser

Oyuna is one of three curriculum advisers at the city education office in Ulaanbaatar, Mongolia. Over the winter she has been put on five projects at once: new science textbooks, a teacher training course, an exam review, a reading programme for rural schools and the office's annual report. Each project leader asks for a day of her week, and each complains that her work arrives late.

She keeps a log for a fortnight. Her days are cut into pieces of an hour or two, she spends the start of most pieces finding where she left off, and draft chapters wait a week for her comments because she reaches each project only once a week. She takes the log to her director, who agrees to pause the annual report and pass the exam review to a colleague. With three projects and whole mornings for each, her comments on the textbook drafts come back in two days instead of eight.

Try this today Tomorrow, make a mark each time you move to a different task. At the end of the day, count the marks and circle the ones you chose.

More on this trap: Context switching →

Question 1 of 2

Musa, a site engineer in Kano, Nigeria, works on four building projects, a day or so on each per week. Contractors on every site say they wait days for his answers.

What is the main cost of the way Musa's time is shared?

Question 2 of 2

A secondary school in Quito, Ecuador, plans to speed up its curriculum review by asking all twelve of its teachers to give one hour a week to it, alongside their classes. Nestor, the deputy head, has doubts.

What is the weakness in the school's plan?