Lesson · 6 min Gentle
The Cost of Late Faults
In one line A fault costs more to fix the later it is found, because more work has been built on top of it.
A mistake costs least on the day it is made. A wrong figure on a drawing can be fixed with a pencil. Once a wall is built to that drawing, the same mistake means demolition, new materials and a delay to everything that follows. The fault itself has not grown. What has grown is everything built on top of it.
Barry Boehm, an American software engineer, gave this pattern numbers. Gathering data from large software projects, and setting it out in Software Engineering Economics (1981), he showed that a fault fixed after delivery cost many times more than the same fault caught while the requirements and design were being written. In a 2001 summary with Victor Basili, the rule of thumb was that a fix after delivery is often a hundred times dearer than one made at the requirements and design stage. Building shows the same shape: a drain misplaced on paper costs minutes to move, and in a finished floor, days.
The famous curve has limits, and Boehm said so. In that 2001 summary the authors added the word 'often', noting that for small systems where little is at stake the ratio was nearer five to one, and that a design divided into well-separated parts could keep late fixes fairly cheap even in large ones. So the hundred is not a law of nature. The direction, though, holds in most kinds of work: later costs more.
The practical lesson is modest. A few minutes spent reading a plan back, checking a drawing against the site, or showing a sketch to a user buys more than days of repair later. Earlier in the course, Build It In, Don't Inspect It In argued that quality comes from how the work is done; the cost curve says when to look hardest, which is at the start.
Go deeper
Why does a late fault cost so much more? Three things add up. More work rests on it: walls on the slab, screens on the database, so more must be undone. Finding it is harder, because the symptom shows up far from the cause and someone has to trace it back. And a fault found by a user carries costs beyond the repair: lost trust, compensation, a recall, sometimes harm. The first two grow with the size of the project, which helps explain why Boehm found the ratio so much larger in big systems than in small ones.
Twenty minutes before the pour

Emre is the site engineer for a two-storey extension to a primary school in Mersin, Turkey. The ground-floor slab is due to be poured on Monday. On Friday afternoon he sits down with the plumber and lays the structural drawings over the plumbing drawings, one sheet at a time. Twenty minutes in, they find it: the drain for the new toilets is marked on the wrong side of a beam, where it could never connect.
Moving it on paper takes a quarter of an hour and a phone call to the designer. Emre remembers the school's other block, built two years earlier, where the same kind of mistake surfaced only after the floor was tiled. That time it took a jackhammer, a new run of pipe, new tiles and three weeks in which two classrooms could not be used. The fault had been the same size. What had changed was how much stood on top of it.
Try this today Before you send or start something today, spend five minutes checking it with fresh eyes, and note anything you would have had to undo later.
Cite or share this lesson
A plain reference you can paste into notes or an essay:
Quest2Plan. “The Cost of Late Faults.” https://quest2plan.com/learn/lesson/the-cost-of-late-faults. Accessed 29 November 2026.