The Channel Tunnel
In one line Between Britain and France, rules that changed after the price was set helped push the tunnel's cost far above plan.
On 12 February 1986 Britain and France signed the Treaty of Canterbury, agreeing to a fixed link under the Channel. It would be built and run by private companies under a long concession and paid for by private money: shares, and loans from a large group of banks. The treaty also set up an Intergovernmental Commission, advised by a Safety Authority, to oversee construction and operation for both governments, and it drew a border between the two countries in the middle of the tunnel.
Two groups of five construction firms, one British and one French, each built a terminal and bored from their own coast, joined in a bi-national organization called TransManche Link. The rock differed: on the French side the chalk was harder and more fractured, and machines ran sealed for the first five kilometres. Tunnelling began in 1988, and on 1 December 1990 the service tunnel broke through, the two halves meeting about 30 centimetres apart. Ten workers, eight of them British, were killed during construction.
The tunnel opened on 6 May 1994, a year late. Measured in 1985 prices, its construction had been expected to cost 2.6 billion pounds; it came to 4.65 billion, an overrun of about 80 per cent, partly from safety, security and environmental demands raised as work went on. Financing cost about 140 per cent more than forecast, and in 1995 the operating company suspended payments on its debt.
Look at who decided what. Two governments set the rules but did not pay for them; private lenders paid but could not change the rules; and every month of delay added interest. Each new demand might be wise, but a design priced before its rules were settled, between two languages and two legal systems, is built to overrun.
One rulebook for the bridge

Chanthavy is the lead engineer for the Lao side of a road bridge into Thailand, built jointly with a Thai team. In the first month she finds that the two sides follow different standards for railings, loads and lighting, and that the drawings are labelled in two languages.
Before any concrete is poured, she and her Thai counterpart agree on a single rulebook for the whole bridge, with one set of drawings in a shared language and both sides' safety officers signing it. They set up a joint change board that meets every two weeks, where any new requirement must come with its cost and who will pay it. When a road safety agency asks for wider footpaths halfway through, the request goes to the board, the cost is shared as agreed, and the steel order is changed before it ships.
Try this today List who sets the rules on a project you know and who pays for them. Notice where the two are not the same people.
Cite or share this lesson
A plain reference you can paste into notes or an essay:
Quest2Plan. “The Channel Tunnel.” https://quest2plan.com/learn/lesson/the-channel-tunnel. Accessed 29 November 2026.
Sources
- Channel Tunnel — Encyclopedia article on the tunnel's construction, geology, costs and finance.
- Treaty of Canterbury (1986) — The treaty that set up the concession, the Intergovernmental Commission and the border in the tunnel.