Lesson · 6 min Stretch
The Case Against Estimating
In one line Critics of estimating say slice work small and count what finishes; defenders reply that budgets and dates still need forecasts.
Some software developers and coaches argue that much of the estimating done in their trade should stop. Their case, often gathered under the label 'no estimates', is stronger than its slogan. Detailed estimates take real time from the people who would otherwise be doing the work. They are made at the start, when least is known. And in many organizations they do not stay forecasts: a guess becomes a deadline, the deadline becomes a stick, and the team learns to pad every number, which makes the estimates worse still.
What they offer instead is a different kind of knowledge. Cut the work into small slices of similar size, each worth something on its own, so that counting slices is nearly as good as sizing them. Finish slices often, and forecast from how many actually get finished each week. Earlier in the course, Slices That Matter showed how to cut work this way, and Velocity and Its Abuse showed how a number turns against a team once it becomes a target.
The replies are strong too. Somebody has to decide whether to fund the work, hire the staff, sign the contract or promise a launch to customers, and those decisions need some view of cost and time. Forecasting from finished slices is itself a kind of estimate, and it needs a history that a new team or a new kind of work does not have. Critics add that poor estimates are mostly a lack of skill, which can be learned, and that giving up estimates because they are misused is like giving up maps because some are wrong.
Much of the argument turns on context. A team that releases small changes to its own product every day can lean on counting; a builder pricing a bridge or a charity bidding for a grant usually cannot. How estimates are treated once given is the subject of later lessons this week.
Go deeper
Two points are often lost in the noise of the debate. First, the defenders of estimating usually agree that an estimate, a target and a commitment are different things, a distinction drawn in When the Boss Wants a Smaller Number, and that much of the harm comes from blurring them rather than from estimating itself. Second, much of the evidence on both sides is practitioners' stories rather than careful studies. Supporters describe teams that work happily without estimates; critics describe businesses that could not plan without them. Both kinds of story are real, which suggests the answer depends on the work and the setting more than on a general rule.
A trial without hours

Farid leads a team of six building a booking app for a group of clinics in Tunis. Every quarter his manager asked for an hour-by-hour estimate of each feature, and the team spent two full days producing them. The figures were then quoted back as promises. Farid proposes a trial: for one quarter the team will split work into pieces of no more than two or three days, stop estimating hours, and report how many pieces finish each week, with a forecast drawn from that count.
By the end of the quarter the team has saved its two days of estimating meetings and finishes about nine pieces a week, give or take two. The manager likes the steadiness but raises a problem: the clinics' owners must decide in March whether to fund a second app, and they want a cost. Farid counts the slices the second app would need, divides by the weekly pace and gives a range. He admits, with a smile, that it is an estimate after all, made a different way.
Try this today Count the hours your team spent estimating last month, and list the decisions those estimates actually changed.
Cite or share this lesson
A plain reference you can paste into notes or an essay:
Quest2Plan. “The Case Against Estimating.” https://quest2plan.com/learn/lesson/the-case-against-estimating. Accessed 29 November 2026.
Sources
- Why the #NoEstimates movement wants to remove effort estimations (Built In) — A journalist's account of the case for working without estimates, with the replies of its critics.
- 17 Theses on Software Estimation (Expanded) — A defence of estimating: the business decisions estimates feed, and estimates, targets and commitments told apart.
- Software development effort estimation — What research says about how accurate software estimates are and how they are used.