The Building That Took a Year

In one line The Empire State Building rose in about 410 days because its builders treated the schedule as a sequence to feed.

In 1930 and 1931 builders in New York put up the Empire State Building, 102 storeys tall, faster than almost anyone thought possible. Digging began on 22 January 1930 and work on the building itself on 17 March. It was structurally complete on 11 April 1931, 410 days after construction began, and opened on 1 May, the date the owners had demanded. Work started a few months after the Wall Street crash of October 1929.

The contractors, Starrett Brothers and Eken, treated the job as a sequence. The steel frame rose at about four and a half storeys a week; in July 1930, 22 storeys of steel went up in 22 working days. The site in midtown Manhattan had almost no space to store anything, so steel was ordered two floors at a time and delivered as it was needed. At one point more than 200 trucks a day brought materials up a temporary driveway, and a small railway with carts on each floor carried them from the hoists to the work. Close behind the steel came the crews casting floors, and behind them the plumbers, electricians and plasterers, floor by floor.

The method came decades before anyone named the critical path, but it is the same idea seen in practice: the frame and floors set the pace, and everything else was arranged to keep that chain fed, as The Critical Path describes. The steel was topped out on 19 September 1930, twelve days ahead of schedule, and the building cost about 41 million dollars, less than had been budgeted.

The speed had a price. At the peak, 3,439 men worked on a single day, many of them high on open steel; Lewis Hine photographed them there. Official accounts say five workers died. Newspapers reported more, though those claims were never confirmed. Any story of a schedule kept so well should count them too.

A tower with nowhere to put things

Illustration: A tower with nowhere to put things

Iskander is the site manager for an office block on a narrow street in the old centre of Tashkent, Uzbekistan. There is no yard, the street can be closed to lorries only at night, and his first month was chaos: steel bundles blocked the gate while the concrete mixers queued round the corner.

He had read how the Empire State's builders worked, and changed two things. He stopped ordering materials by the month and ordered them by the floor, each load booked for a set night so that it arrived just before the crew needed it. And he set the trades to follow one another up the building, the frame first, the floor slabs two levels behind it, the services two levels behind those. The street grew quiet in the day, the gate stayed clear, and the frame began to rise at a steady pace that the whole site could plan around.

Try this today Think of a job with no room to store anything, such as cooking in a small kitchen. What would you need to arrive just when it is wanted?

Question 1 of 2

A builder is putting up flats on a cramped street in Tripoli, Lebanon, with no space for storing steel or blocks on site.

Which practice from the Empire State Building fits his problem?

Question 2 of 2

On a tower in Baku, Azerbaijan, the plumbers, electricians and plasterers are each waiting until the whole frame is finished before they start.

What would the Empire State's builders have done differently?