When the Boss Wants a Smaller Number
In one line An estimate is a forecast, a target is a wish and a commitment is a promise; keep them apart when pressed.
Three different things get called 'the estimate', and much grief comes from mixing them up. An estimate is a forecast: how long the work will probably take, given what is known. A target is a wish: the date someone would like, often for good reasons, such as a funding deadline or a festival that will not move. A commitment is a promise: the date the team agrees to meet, chosen knowing both the forecast and the wish. Researchers on software estimation have long complained that one word is used for the planned effort, the budget and the price quoted to a client, though each serves a different purpose.
The trouble starts when a sponsor hears an estimate and asks for a smaller one. If the team simply gives a smaller number, nothing about the work has changed; only the forecast has become less true. Everyone then plans around a date that was never likely, and when the overrun comes it is blamed on the team. A harder version is deliberate: estimates set low to win approval, which the researchers Jones and Euske called strategic misrepresentation.
A better reply keeps the estimate fixed and opens the target and the commitment for discussion. 'Our forecast is nine to twelve weeks. To promise eight, something has to change: drop these two features, add a second crew, accept a simpler finish, or carry the risk of missing it.' The sponsor can then choose. Earlier in the course, Asking the Sponsor to Choose showed this kind of trade.
Pressure is not always wrong. A sponsor who pushes back may know of a shortcut, or may be testing whether the estimate rests on anything. Ambitious targets can draw out ideas a cautious team would not have found. The line is crossed when a target is written down as if it were the forecast, and nobody tracks the gap between them.
Go deeper
Why do sponsors push for smaller numbers? Often because they face pressure of their own: a board that approves only projects below a certain cost, a minister who wants a ribbon cut before a fixed date, a client comparing bids. Seen that way, the sponsor's request is information about a target, not a judgement on the estimate. A team that answers with options gives the sponsor something to take back up the line. The research on large public projects suggests the alternative is costly: plans that win approval by looking cheaper and quicker than they are tend to overrun, and the overrun then lands on the team rather than on the promise.
Two classrooms before term

Mercedes runs a small building firm in the Mexican city of Puebla. A school asks her to add two classrooms during the summer break, and her estimate, built from her records of similar jobs, is nine to eleven weeks. The school's director has seven weeks before term and asks, kindly but firmly, whether she could say seven.
Mercedes keeps her forecast. 'I believe it will take nine to eleven weeks,' she says. 'Seven is your target, and it is a fair one. To promise it, some things would have to change: we pour the foundations before the break starts, you accept painted block walls instead of plaster this year, and I bring in a second crew at extra cost.' The director agrees to the early foundations and the plain walls but not the second crew. With those changes Mercedes forecasts seven to nine weeks, and they agree the two classes will use the library for the first fortnight if needed. The rooms are ready in eight weeks.
Try this today Next time someone asks for a shorter date, say what would have to change to reach it, and ask them to choose.
Cite or share this lesson
A plain reference you can paste into notes or an essay:
Quest2Plan. “When the Boss Wants a Smaller Number.” https://quest2plan.com/learn/lesson/the-boss-wants-a-smaller-number. Accessed 29 November 2026.