The Big Dig
In one line Boston buried a highway in tunnels at five times its first estimate, and still argues over whether the result was worth it.
In 1959 an elevated six-lane highway, the Central Artery, carried about 75,000 vehicles a day through downtown Boston, in the United States. By the 1980s it was jammed for hours and cut the city off from its waterfront. The Central Artery/Tunnel Project, known as the Big Dig, planned from 1982, would put the highway into tunnels and extend the interstate to the airport. It was first expected to cost 2.8 billion dollars and to be finished in 1998.
Politics shaped it from the start. Federal money depended on Congress, and in 1987 Congress overrode a presidential veto of the highway bill that funded it. A seven-year environmental review let inflation raise the estimate. The city of Cambridge sued over a design with ramps stacked beside the Charles River, forcing a redesign. Clean-air law required public transport projects as mitigation. Each deal won support and added scope.
Construction ran from 1991 to 2007, and the project was completed at 14.6 billion dollars, about five times the first figure, and more with interest. Leaks appeared in the tunnels. On 10 July 2006 concrete ceiling panels in a connector tunnel fell on a car, killing a passenger. The national safety board found that the epoxy used to anchor the ceiling bolts was not suited to bearing loads for long periods. Contractors later paid over 450 million dollars to settle claims about the work.
How should a city judge it? Travel times on the old route fell sharply, a long park replaced the elevated road, and soil from the tunnels rebuilt an island in the harbour. Against that stand the cost, the death and years of disruption. Measured against the first estimate it failed; measured against the city it left, many think it succeeded.
Three numbers for the auditor

Damián is an auditor for the state government of Jalisco, Mexico, asked to report on a ring road around Guadalajara that was partly buried in tunnels. The first estimate, made nine years before opening, was 400 million dollars; the final cost was 1.3 billion.
Rather than report one overrun, Damián sets out three comparisons. Against the first estimate, the road cost more than three times as much. Against the budget approved once the tunnels, a new bus line and the noise walls had been added, it ran 35 per cent over. Against the choice of doing nothing, the record shows journey times on the main corridor cut by a third, though traffic on side streets has grown. His report recommends that future estimates be given as ranges, and that each later addition be costed and approved openly, so the next auditor can tell overrun from new scope.
Try this today Pick a project you know that ran over. List what was added to it after the first estimate, and what simply cost more.
Cite or share this lesson
A plain reference you can paste into notes or an essay:
Quest2Plan. “The Big Dig.” https://quest2plan.com/learn/lesson/the-big-dig. Accessed 29 November 2026.
Sources
- Big Dig — Encyclopedia article on the Central Artery/Tunnel Project, its costs, politics and results.
- Big Dig ceiling collapse — The collapse of 10 July 2006, its cause and its aftermath.