
Lesson · 6 min Gentle
Test as You Go
In one line Testing each piece as it is made finds faults while they are small and cheap, and gives a project a steady rhythm.
There are two ways to test a building or a program. One is to finish the whole thing and then test it. The other is to test each piece as it is made, before anything else is built on top. The first feels faster, because testing waits until the end. It is usually slower, because the faults it finds are buried under everything that followed, and they all arrive together in the last weeks, when there is least time to fix them.
Good builders work the second way. Before concrete is poured, someone checks the steel, the levels and the pipes set into the floor. Before walls are closed up, the wiring and plumbing are tested while they can still be reached. Each floor is checked before the next goes up, and in many countries building inspectors visit at set stages for the same reason. Earlier in the course, The Cost of Late Faults showed why this pays: a fault caught at its own stage is cheap.
Software teams learned to work the same way. From the 1990s many began to test every change as soon as it was made. Each programmer writes small automatic tests for the piece they have built, and a shared machine puts the whole program together and runs all the tests several times a day. The practice, known as continuous integration, means a fault shows up within hours of being made, while the person who made it still remembers why.
Testing as you go changes a project's rhythm. Instead of a long build followed by a long, anxious test phase, work moves in short loops: make, check, fix, move on. The cost is real: tests take time to write and keep up, and tests that are slow or unreliable soon get skipped. Some things, such as how a whole building behaves in a storm, can only be seen at the end.
Go deeper
Testing as you go also guards what is already done. Each change can break something that used to work: a new pipe pressing on an old cable, a new screen upsetting an old calculation. Running the earlier tests again after every change, which software teams call regression testing, catches these breaks quietly. A common habit is to give every fault that is found its own small test, so that the same fault cannot slip back in unnoticed.
One floor at a time

Felipe is the foreman on a four-storey health centre in Ambato, Ecuador. On his last job, the plumbing was tested once the building was finished. A leaking joint on the ground floor meant breaking open plastered walls on three floors to find it, and the handover slipped by a month. This time he does it differently.
Before each slab is poured, Felipe and the engineer walk the deck with the drawings: spacing of the steel, ducts, sleeves for pipes. On the second floor they find a sleeve for a drain missing, and fixing it takes an hour. Before the walls on each floor are plastered, the plumber fills the new pipes and leaves them under pressure overnight; one weeping joint on the third floor is remade the next morning. The tests take a little time every week. When the health centre is handed over, the last week is quiet, because there is nothing left to find.
Try this today In something you are making this week, check the first piece properly before you start the second.
Cite or share this lesson
A plain reference you can paste into notes or an essay:
Quest2Plan. “Test as You Go.” https://quest2plan.com/learn/lesson/test-as-you-go. Accessed 29 November 2026.
Sources
- Continuous integration — How software teams merge and test every change, the practice's history, and its costs and limits.
- Building inspection — How inspectors check buildings, including at different stages of completion.