Lesson · 6 min Steady
Managing by Stages and Exceptions
In one line Give a manager clear limits, let them decide freely inside them, and have the board decide only what falls outside.
A council board cannot run a building project day by day, and its project manager cannot ask permission for every choice. PRINCE2 is a method built around that problem. It grew from PRINCE, which a British government agency adopted for its computer projects in 1989, and was released in 1996 as a method for any kind of project. Its manuals are long, but the main ideas fit in a few plain sentences.
Keep asking whether the project is still worth doing: the business case, described in The Business Case, is looked at again at the end of every stage, and a project whose reasons have gone is closed. Manage in stages: the board commits to one stage at a time, with a detailed plan only for the next stage and a rough one beyond. Be clear about roles, with a small board speaking for those who pay, those who will use the result and those who supply it. Describe what each piece of work must produce before it starts.
The idea that most changes daily life is managing by exception. The board sets limits, called tolerances, on such things as time, cost, scope and risk: finish within two weeks of the date, spend within five per cent of the budget. Inside those limits the manager decides alone and reports as usual. When a forecast shows a limit will be broken, the manager raises an exception, and the board decides.
Supporters say this frees managers, saves the board's time, and lets stage ends stop runaway projects. Critics say the paperwork swamps small projects, and that because any failure can be blamed on poor tailoring, the method is hard to test. Much depends on limits wide enough to trust people inside them.
Go deeper
The idea of managing by exception is far older than PRINCE2. Frederick Taylor, the American engineer behind scientific management, set it out in Shop Management in 1903: a manager should receive short reports on the usual run of work and look closely only at what departs from the expected, good or bad. Taylor's version flowed upward as reports to a manager at the top. The project version adds limits agreed in advance, so the person closest to the work knows exactly where their freedom ends.
Soft ground under the fish market

Amani manages the rebuilding of a market for the county government in Kisumu, Kenya. The board has given her two weeks of tolerance on time and five per cent on cost for the current stage. In the first month she moves the roofing order to a cheaper supplier and swaps two jobs to dodge the rains. She tells the board at the monthly report, not before.
Then the ground under the fish section turns out to be soft, and new foundations push her forecast to nine per cent over budget. That is outside her limit, so she writes a short exception report: what happened, three options with their costs, and her recommendation. The board meets within the week. It moves the fish section to a later stage, keeps the rest on budget, and sets her fresh tolerances for what remains.
Try this today Write down the limits within which you can decide alone at work. If you cannot name them, ask your manager what they are.
Cite or share this lesson
A plain reference you can paste into notes or an essay:
Quest2Plan. “Managing by Stages and Exceptions.” https://quest2plan.com/learn/lesson/stages-and-exceptions. Accessed 29 November 2026.
Sources
- PRINCE2 (Wikipedia) — Origins in 1989 and 1996, its principles, tolerances and managing by exception, and criticisms.
- Management by exception (Wikipedia) — The general idea and its roots in Frederick Taylor's Shop Management of 1903.