Scrum in Brief

In one line Scrum runs work in short fixed cycles, with a product owner, developers and a scrum master, and leaves much to the team.

Scrum takes its name from the rugby article of 1986, described earlier this week in The Rugby Approach. Ken Schwaber and Jeff Sutherland, who had each been trying its ideas with software teams, presented their method together at a conference in Austin, Texas, in 1995. They now keep a short, free document, The Scrum Guide, which calls Scrum 'a lightweight framework'.

A Scrum team is usually ten people or fewer, with three kinds of responsibility. The product owner keeps a single ordered list of the work and decides what matters most. The developers decide how to do the work and how much of it fits. The scrum master helps the team and the wider organization use Scrum well and clears obstacles out of the way.

Work runs in sprints, fixed cycles of a month or less, often two weeks. Each sprint opens with planning: the product owner brings the ordered list, everyone agrees a one-sentence sprint goal, and the developers choose what they can finish, judging by what they really finished lately and by who will be away, then break the first items into tasks of a day or less. A fifteen-minute Daily Scrum, the stand-up met in The Daily Stand-up, follows each day. At the end a sprint review shows finished work to the people it serves, and a retrospective looks at how the team worked. Finished means meeting the team's definition of done.

Much is left open on purpose. The guide calls the framework 'purposefully incomplete': it sets no way to estimate, no charts and no engineering practices. Teachers have used it too; in the Netherlands the chemistry teacher Willy Wijnands ran classes in sprints with pupils in teams of four. The common failure is simpler: a sponsor crams the sprint with everything urgent and calls it the team's promise.

Sprints in the chemistry lab

Illustration: Sprints in the chemistry lab

Lieke teaches chemistry at a secondary school in Utrecht, in the Netherlands. For a five-week module on water quality she splits her class into teams of four, each with a board of three columns: to do, doing, done. She acts as product owner. At the start she gives every team the module's goal and an ordered list of what they must learn and show, from measuring acidity to explaining how a treatment plant works.

In the first sprint one team chose eight items and finished three; at the review, in front of the class, they could explain nothing about filtration, which they had marked as nearly done. At the next planning Lieke asked them two questions: how much did you really finish last time, and who is away this sprint? Two members were going on a school trip. The team chose four items, wrote a goal across the top of the board, 'we can test a water sample and explain the result', and finished all four.

Try this today Before your next week begins, write one sentence saying what the week should achieve, then pick only the tasks that serve it.

In the Toolkit, step by step: Sprint planning →

Question 1 of 2

At sprint planning for a banking app in Ho Chi Minh City, Vietnam, the sponsor tells the team that all eight urgent items must go into the next two weeks.

In Scrum, who decides how much work goes into the sprint?

Question 2 of 2

Kwesi, the scrum master on a team in Kumasi, Ghana, hands each developer a task every morning and sends the director a weekly report of everyone's hours.

How does Kwesi's work differ from the scrum master's job as the guide describes it?