Room to Slip

In one line Float is how long a task can slip without moving the finish, and once it is spent it is gone.

Every task off the critical path has some room: time it can slip without delaying the end of the project. Planners call this float, or slack. It is found from the two walks through the network: a task's latest possible start minus its earliest possible start. A task on the critical path has none.

Take a garage build. The slab takes 5 days, the walls 4 and the roof 3, one after another, so the build takes 12 days. The driveway takes 3 days and can be laid any time after the slab is done. Its earliest start is day 5, and it must be finished by day 12, so its latest start is day 9. It has 4 days of float.

Float belongs to a chain, not to each task in it. If the garage doors (2 days) must be fitted before they are painted (1 day), and the pair has 4 days of float, it is shared. Should the fitting slip by 3 days, the painting has only 1 left. Each team may think the spare days are its own, and they cannot both use them.

Two habits follow. First, float spent early is float gone. A task started late because it has room has nothing left when something goes wrong, the trap of Starting at the Last Minute in a new form. Second, a task with little float deserves early attention. It is not on the critical path, so nobody watches it, but one bad week puts it there. Many projects are finished late by a task that was almost critical, not by one that was.

Go deeper

Planners distinguish two measures. Total float is how long a task can slip without delaying the end of the project. Free float is how long it can slip without delaying the next task. In the garage, the door fitting may have 4 days of total float but no free float at all, because the painting is waiting for it. Total float is shared along a chain; free float belongs to one task alone. A task can have plenty of total float and still hold up a colleague the moment it slips.

The dress and the invitations

Illustration: The dress and the invitations

Kibet was organizing his sister's wedding in Eldoret, Kenya, ten weeks away. Everyone around him was worried about the invitations, which felt urgent. He sat down one evening and worked out the room each task had.

The invitations needed two weeks to settle the guest list and one week to print, and had to be posted four weeks before the day: three weeks of float. The dress was another matter. The fabric would take two weeks to arrive, the tailor needed six weeks to make it, and the final fitting had to be in week nine. That chain had just one week of float. Kibet ordered the fabric the next morning, and let the guest list wait. The fabric came a week late, which used the whole week, so from then on he rang the tailor every Friday. The invitations went out on time anyway, and the dress was ready for its fitting with two days to spare.

Try this today List three things you must do before a fixed date. For each, how late could you start and still make it? Start first the one with least room.

Question 1 of 2

A school sports day in Jaffna, Sri Lanka, is 20 days away. The banners take 4 days to print and can start as soon as the logo is approved on day 6.

How much float do the banners have?

Question 2 of 2

For a conference in Salalah, Oman, ordering the chairs and then delivering them form a chain with 6 days of float. The chair order has just slipped by 4 days.

How much room does the delivery have left?

Cite or share this lesson

A plain reference you can paste into notes or an essay:

Quest2Plan. “Room to Slip.” https://quest2plan.com/learn/lesson/room-to-slip. Accessed 30 November 2026.

Sources