Risks Worth Taking

In one line An opportunity is an uncertain event that would help, and it can be planned for as carefully as a threat.

Uncertainty cuts both ways. A risk register usually lists only threats, but the same uncertainty that might bring a flood might bring a windfall: a grant reopened, a supplier with spare stock, a result better than expected. Many risk standards treat these good possibilities as risks too, and call them opportunities. They can be found, rated and owned in the same way as threats.

The four responses have mirror images. Instead of avoiding a threat, a team can change the plan to make an opportunity more likely to happen. Instead of reducing harm, it can enlarge the benefit if the chance comes. Instead of passing a threat to someone better placed, it can team up with a partner who can help seize the chance. And it can accept an opportunity, ready to take it if it arrives but spending nothing now. A charity that knows a foundation sometimes has money left at the end of its year can keep a costed proposal ready on the shelf.

Science is full of chances taken by people prepared to notice them. In 1928 Alexander Fleming came back from a summer holiday to his laboratory at St Mary's Hospital in London and saw that a mould on one of his culture plates had stopped the bacteria near it from growing. He might have thrown the plate away. Instead he photographed it, kept the mould and repeated the test. Luck supplied the mould; his habits turned it into a finding.

Why do teams so rarely plan for good surprises? Partly because threats feel more urgent, and guarding against loss feels more responsible than chasing gain. Partly because a register is often set up to report danger to a sponsor, not to spot openings. A team whose register holds no opportunities is probably missing some.

Ready for a spare slot

Illustration: Ready for a spare slot

Duong leads a small research group at a university in Can Tho, Vietnam, breeding rice that tolerates salty water. The group's work waits on genetic sequencing at a national centre, where the queue is months long. Its register has the usual threats, and one opportunity: other labs sometimes cancel, and the centre then offers their slots at short notice to whoever is ready.

Duong gives the opportunity an owner, a doctoral student, and a response. The group keeps its next batch of samples prepared, labelled and frozen, with the paperwork filled in, so it could send them within two days. It also writes a joint grant proposal with a partner university in the Philippines, which has its own sequencing machine, in case that funding comes through. In October the centre emails on a Thursday: a slot has fallen free for Monday. Duong's group is the only one ready, and its results arrive four months early.

Try this today On a plan of yours, write one thing that might go unexpectedly well. What would you need ready to make the most of it?

Question 1 of 2

A charity running reading clubs in Madaba, Jordan, hears that a publisher sometimes gives away unsold children's books at the end of its year.

How could the charity plan for this?

Question 2 of 2

Ayodele is training staff at a health charity in Ilorin, Nigeria, and writes the word 'opportunity' on the board.

Which definition should Ayodele give?

Cite or share this lesson

A plain reference you can paste into notes or an essay:

Quest2Plan. “Risks Worth Taking.” https://quest2plan.com/learn/lesson/risks-worth-taking. Accessed 29 November 2026.

Sources
  • History of penicillin — Fleming's chance observation at St Mary's Hospital in 1928 and what he did with it.
  • Serendipity — Lucky discoveries made by chance, and the word's origin in a letter of 1754.