A Risk or an Issue?

In one line A risk might happen and is planned for ahead; an issue has happened and is dealt with now.

Two kinds of trouble sit on every project, and they need different handling. A risk is something that might happen: rain on the night of an outdoor concert, a supplier who may deliver late, a nurse who may not finish training in time. An issue is something that has already happened: the rain is falling, the delivery did not come, the nurse has resigned. One is uncertain and lies ahead; the other is certain and here now.

The difference decides what you do. A risk is handled in advance, while there is still time and choice: book a covered stage, order early, train a second nurse. Some risks are worth a small cost now to avoid a large one later; others are cheap enough simply to watch. An issue leaves no room for weighing chances. Someone must act today, and the questions become who, with what, and by when.

Mixing the two wastes effort both ways. A team that treats every risk as an emergency wears itself out on things that never happen. A team that treats an issue as a risk keeps discussing how likely it is while the damage spreads. A common warning sign is a risk list that has not changed in weeks while real problems pile up elsewhere, unrecorded. Earlier in the course, The Risk Nobody Mentioned showed how risks are often seen but never said; telling the two kinds apart is the next step.

The line between them moves. Every issue was once a risk, whether or not anyone wrote it down. When a listed risk comes true, it leaves the risk list and joins the issues, with a person and a deadline. The issues nobody listed are a reminder that no risk list is ever complete.

Fourteen lines, two lists

Illustration: Fourteen lines, two lists

Adaeze is managing the opening of a new maternity clinic in Abeokuta, Nigeria, due to see its first patients in six weeks. At the Monday meeting her list has fourteen lines, all treated alike. She splits it in two. Some things might happen: the generator may not be installed in time, the state inspection may ask for changes, and two midwives on loan from the general hospital may be called back. Others have already happened: the ultrasound machine arrived with a cracked screen, and the water tank leaks.

For the second group she wants a name and a date by Friday. The supplier will replace the screen, and a plumber is booked for Wednesday. For the first group she asks a different question: what can we do now that makes this less likely, or less painful? The team asks the inspector to visit early, and asks the general hospital to confirm the midwives in writing. The generator stays on the watch list. The meeting is shorter than last week's, and nobody spends twenty minutes debating whether the leaking tank might leak.

Try this today List three worries about something you are organizing. Mark each R if it might happen, or I if it already has.

Question 1 of 2

Three weeks before an open-air music night in Tarija, Bolivia, the long-range forecast gives a fair chance of storms on the evening itself.

How should the organizers treat the possible storm?

Question 2 of 2

Bolat runs the kitchen at a hospital in Shymkent, Kazakhstan. On Tuesday morning the main oven breaks down, and two hundred patient lunches are due at noon.

What does this situation call for first?

Cite or share this lesson

A plain reference you can paste into notes or an essay:

Quest2Plan. “A Risk or an Issue?.” https://quest2plan.com/learn/lesson/risk-or-issue. Accessed 29 November 2026.

Sources
  • Risk — What risk means: the possibility of something bad happening, and how different fields define and measure it.
  • Issue log — A project's running list of open and closed issues, ranked by type and severity.