Reading the Earned Value Numbers
In one line Two ratios from earned value show the health of cost and schedule and forecast the final bill, if read with care.
Two ratios boil earned value down to a pair of numbers. Earlier in the course, Earned Value in Plain Words compared three sums: the value of work planned by now, the value of work actually finished, and what that finished work cost. The cost performance index (CPI) divides earned value by actual cost: 0.8 means each pound or dollar spent has bought eighty pence or cents of planned work. The schedule performance index (SPI) divides earned value by planned value: 0.9 means nine-tenths of the work planned by now is finished. Above 1 is good news; below 1 is bad.
Their great use is forecasting. Dividing the whole budget by the CPI gives a rough estimate of the final cost: a 10 million job running at 0.8 is heading for about 12.5 million. Around 1990, researchers at the US Air Force Institute of Technology, guided by David Christensen, studied cost reports from American defence contracts. They found that once a contract was about a fifth complete, its cumulative CPI seldom moved much afterwards, and when it moved it tended to get worse. Overruns show early, and rarely cure themselves. Later studies of other kinds of project found the index settling later, so the pattern is a warning, not a law.
The ratios also mislead. SPI is counted in money, not time, so at the end of a project, when all the planned work has been earned, it returns to 1 even if the job finished months late; in 2003 Walt Lipke proposed earned schedule, which measures the delay in time, to fix this. An SPI can look healthy while the critical path is stuck, if easier work elsewhere races ahead. And neither ratio sees quality: work counted as earned may have to be done again.
So read the two numbers together, watch their trend over several months, and ask what lies behind them. A CPI of 0.85 is not a verdict. It is the start of a question.
Go deeper
Earned value grew up in defence, and some of its hardest lessons came from there. The US Navy's A-12 Avenger II, a carrier-based attack aircraft, was cancelled in January 1991 after its costs and delays grew and its weight ran well over specification. It is often cited as a programme whose performance problems showed in its earned value data, and the legal dispute between the government and the contractors over the cancellation lasted more than twenty years.
A fifth done, a quarter over

Faris was the client's engineer on a new wing for a hospital in Irbid, Jordan, with a budget of 24 million dinars. At the end of the eighth month the contractor's report showed a planned value of 6 million, an earned value of 5 million and an actual cost of 6.25 million. The contractor's covering note said the extra spending would be recovered in the finishing works.
Faris worked out the ratios. The CPI was 0.8 and the SPI about 0.83, with the job only a fifth done. Dividing the budget by the CPI gave a forecast of about 30 million dinars. He knew the research on defence contracts: an index this early seldom recovers. He also looked behind the SPI and found that the delay sat in the foundations of the main block, on the critical path, so it was real. Instead of waiting, he took the forecast to the hospital's board that month with two options: find more money, or take the second operating theatre out of the plan.
Try this today Take any job with a budget. Divide the budgeted value of the work finished so far, its earned value, by what that work has cost, and see what the answer predicts.
Cite or share this lesson
A plain reference you can paste into notes or an essay:
Quest2Plan. “Reading the Earned Value Numbers.” https://quest2plan.com/learn/lesson/reading-cpi-and-spi. Accessed 29 November 2026.
Sources
- Earned value management — The cost and schedule indexes, the usual forecasts of final cost, and the method's history in defence.
- Earned schedule — Walt Lipke's extension, which measures schedule in time because the money-based index returns to 1 at the end.
- A Review of Cost Performance Index Stability — An Air Force Institute of Technology thesis finding the cumulative index stable from about 20 per cent complete.