
Lesson · 6 min Stretch
Day 4: Three Risks and a Pre-mortem
In one line Picture your project as already failed, write why, then pick the three likeliest, worst risks and decide a response to each.
Plans are written by optimists, and small projects are no exception. On the fourth day, take ten minutes to imagine that it is a week from now and your project has failed. Not 'might fail': has failed. Then write, quickly and honestly, every reason why. This is the pre-mortem from Imagine It Already Failed, which the psychologist Gary Klein described as a way to make doubts easy to say aloud.
If others are involved, ask each of them to write reasons alone before anyone speaks, then read them round, one each in turn, with you going last. On your own, you can still play both parts: write the reasons a sceptical friend would give, including the ones about you. 'I lost interest on day three' and 'I never asked my sister, who owns the van' are as real as rain.
From the list, pick three. The test from How Likely, How Bad? is enough: how likely, and how much harm if it happens. For each, choose one of the responses in Avoid, Reduce, Share, Accept: avoid it by changing the plan, reduce it with a check or a backup, share it with someone better placed, or accept it and know what you will do if it comes. Write each down with a name beside it, even if the name is yours, as Every Risk Needs an Owner insisted.
Three is deliberate. A long risk list on a small project becomes a reason to worry rather than act. The point is to change the plan today: move a task earlier, ask for help now, book the backup. A pre-mortem that leaves the plan as it was has cost ten minutes; one that moves a single task may have saved the week.
Go deeper
Why does treating failure as certain help? In a study published in 1989, Deborah Mitchell, J. Edward Russo and Nancy Pennington asked people to explain events described either as merely possible or as certain. Explanations of events presented as certain tended to be longer and to draw on more specific episodes. The pre-mortem rests on the same idea, sometimes called prospective hindsight. It has a weakness too: because it assumes failure is coming, it can turn up worries that are not real, and the team still has to judge which reasons deserve action.
A pump, a harvest and a money box

The hand pump in Yitbarek's village near Gondar, Ethiopia, needed spare parts, and the five members of the water committee planned a coffee-and-football afternoon to raise the money. Yitbarek, the committee's secretary, made it his practice project. After church on Sunday he asked the others to imagine it was a week later and the day had raised almost nothing, and to write why on scraps of paper before anyone spoke.
The reasons, read round one at a time, included rain, a mechanic who never sent his price, and a clash with the teff harvest that would keep families in the fields. One unsigned slip said the money box was always kept by one man with no written record. They chose three. They moved the day a week later, after the harvest; asked the district water office for the price of the parts; and agreed that two people would count the money and read the total aloud. They accepted the risk of rain: the coffee would move under the church roof.
Try this today Set a timer for five minutes and write every reason your project might have failed by next week. Circle the three you would act on.
Cite or share this lesson
A plain reference you can paste into notes or an essay:
Quest2Plan. “Day 4: Three Risks and a Pre-mortem.” https://quest2plan.com/learn/lesson/practice-three-risks. Accessed 29 November 2026.
Sources
- Performing a Project Premortem — Gary Klein's short article in the Harvard Business Review describing the pre-mortem.
- Gary A. Klein — The psychologist of real-world decision making who described the pre-mortem method of looking at risk.