Phases and Gates

In one line A gate is a real decision to continue, change or stop; gates that never stop anything are only paperwork.

New products and research programmes usually begin with more ideas than money. A phase-gate method divides the work into phases, each ending at a gate: a meeting where people who control the money look at what the phase produced and decide what happens next. NASA ran large projects as phases separated by reviews in the 1960s, and in 1990 Robert Cooper, a professor at McMaster University in Canada who studied new product development, described a version for companies, which he called stage-gate systems.

Each phase is meant to buy information. An early phase may cost a few weeks of study, a later one a factory line, so the gates sit where the next phase costs more than the last. At each gate the gatekeepers have four answers: go on, kill the project, hold it until money or people are free, or recycle it, sending work back to be done again. The criteria are agreed in advance, some as conditions that must be met and some scored. Earlier in the course, The Business Case said a case should be checked again at each main checkpoint; a gate is that checkpoint.

The kill decision is the point. Most new products and research ideas will not work, and stopping one at the second gate costs a fraction of stopping it at the fifth. A gate that never says stop turns into paperwork: teams learn which slides pass, gatekeepers wave through projects they sponsored, and projects end only when the money does.

Supporters say gates bring decisions into the open and let an organization compare its bets. Critics say they slow learning, tempt teams to polish evidence, and force a sequence where overlapping work would be quicker; Cooper himself later described lighter, scalable versions. Much depends on whether anyone is willing to stop.

The third gate

Illustration: The third gate

Cecilia chairs the third gate for a solar food dryer at an appliance maker in Penang, Malaysia. The prototype works well, and the engineers are proud of it. But the costing shows each unit would cost 40 per cent more than the price farmers in the market study said they would pay, and a cost within ten per cent of target was a must-meet condition agreed at the last gate.

The team asks to go ahead anyway: savings will come once production starts. Cecilia asks what evidence there is for that, and nobody has any. She chooses recycle: three weeks to find a cheaper design, and a kill if the gap is still wider than ten per cent. The engineers replace a steel frame with a moulded one and the fan with a smaller one. When the gate meets again the gap is seven per cent, and the project goes on.

Try this today Think of a project you know that was stopped. Was it stopped at a planned checkpoint, or only when the money ran out?

Question 1 of 2

A crop-research institute in Ibadan, Nigeria, has twelve candidate pest-resistant cassava lines. Field trials cost ten times as much per line as greenhouse tests.

Where would a gate do the most good?

Question 2 of 2

Akira is preparing the second gate for a new water meter at a factory in Osaka, Japan.

In what order should the parts of the gate happen?