PERT and the Polaris Missile
In one line PERT made Polaris famous for its planning, but its biggest effect may have been on the people watching.
In 1956 the United States Navy set up a Special Projects Office to build something nobody had built: a ballistic missile that could be fired from a submarine under water. The Polaris programme drew on many contractors, laboratories and navy offices, each making a piece whose timing depended on the others. The office, led by Rear Admiral William Raborn, needed a way to see how the whole effort was going.
Its answer, worked out in 1957 and made public in 1958, was the Program Evaluation and Review Technique, or PERT. Each piece of work became an activity in a network, linked to the activities it waited for, much as in The Critical Path. Because most of the work was new, each activity got three time estimates, best, most likely and worst, combined as Three Numbers Are Better Than One described. A computer added up the chains, found the longest, and judged how likely each date was to be met. On 20 July 1960 the submarine George Washington fired the first Polaris missile from under water, and PERT became famous with it.
The political scientist Harvey Sapolsky studied the programme for his 1972 book The Polaris System Development, and found that PERT mattered far less than its fame suggested. Asking contractors, navy engineers and planning staff who had used the PERT data, he found each group pointing to another. What PERT did well was impress. Its charts and computers persuaded the navy, Congress and the auditors that the programme was firmly managed, and that won it money, priority and freedom from interference.
Both halves of the story teach something. A network of linked tasks with honest ranges helps people see a large project whole. But a planning tool also does political work: it signals control to the people who pay. That can protect a project, and it carries a risk, because a tool kept mainly for show can look healthy while nobody steers by it.
Go deeper
For decades textbooks told the Polaris story as proof that PERT worked. A much later review of Sapolsky's book in a project management journal pointed out that his finding had been largely ignored by the field. It suggested that planning tools do at least three jobs: coordinating work across organizations, building trust and legitimacy with the people who fund and approve a project, and giving everyone a shared picture of a predictable future. A tool can do the second job well while doing little of the first.
The chart on the wall

Sérgio runs the programme office for forty new rural health posts across Nampula province, in Mozambique. The donor asked for a proper scheduling system, so his analyst built one: a network of every task at every site, each with a best, likely and worst time, printed as a coloured chart that covered a whole wall. Visitors from the capital photographed it, and the donor's reports praised the programme's control.
Six months in, Sérgio asked each site supervisor how often they looked at the chart. None of them did. They worked from their own lists and from phone calls with the builders, and the analyst updated the chart from their monthly reports, after the decisions had been made. Sérgio kept the wall for visitors, but added a short call each Monday in which every supervisor named the next task waiting on someone else. The chart was now redrawn from that call, and twice in the next month it showed a clash early enough to fix.
Try this today Pick one chart or report your team keeps. Ask who last changed a decision because of it. If nobody can say, ask what it is for.
Cite or share this lesson
A plain reference you can paste into notes or an essay:
Quest2Plan. “PERT and the Polaris Missile.” https://quest2plan.com/learn/lesson/pert-and-polaris. Accessed 29 November 2026.
Sources
- UGM-27 Polaris — The missile programme, the Special Projects Office and the first launch from a submerged submarine in 1960.
- United States Navy Special Projects Office — The office that ran Polaris and developed PERT in 1957.
- PERT, Polaris, and the realities of project execution — A journal review of Sapolsky's study and its finding about PERT's real role.