People Are Dependencies Too
In one line A schedule can be in perfect order and still impossible, because one person cannot be in two places at once.
A network can say that two tasks may run side by side, and the schedule built from it can be in perfect order, and still it may be impossible, because both tasks need the same person. It is the kind of link that What Must Come First traced to people and tools: not the nature of the work, nor a habit, but a limit on people.
The tightest limit is often one specialist shared by several projects: a laboratory's only technician who can run a particular instrument, or a hospital's only children's anaesthetist. Each project's plan counts on her, and each is reasonable on its own. Put together, they may book her for a week and a half of work in every week. The work then waits in a queue, and each switch from one project to another costs her time.
The remedy is called levelling: moving work in time so that nobody is booked beyond what they can do. Start with the tasks that have float, since they can move without changing any finish date. If there is not enough float, something has to give. A finish date moves, which is the truth the old plan was hiding. Or a second person is trained, the method is changed, or a sponsor decides which project goes first.
Levelling makes plans longer on paper, and teams often resist it. The alternative is a short plan that nobody can meet. A useful habit is to read a schedule twice: once for the order of the work, and once asking, for every task, who will do it and where else they are needed that week.
Three projects, one technician

Kwame is the only technician at a university laboratory in Cape Coast, Ghana, trusted to run its gene sequencer. In February three research projects each planned two weeks of his time in March. Each plan was sound. Together they asked for six weeks of work in a month of four.
The head of the laboratory drew one chart by person instead of by project, and the overlap was plain. A malaria study came first, because its blood samples would spoil. A soil study had float, since its results were not needed until July, so it moved to April. For the third, a plant study, Kwame trained a postdoctoral researcher to do the simpler preparation of samples, so his own part shrank to a week. The month was still full, but no longer impossible, and every project knew its real dates.
Try this today Look at your next two weeks and count the hours other people's plans have asked of you. Is it more than you have?
Cite or share this lesson
A plain reference you can paste into notes or an essay:
Quest2Plan. “People Are Dependencies Too.” https://quest2plan.com/learn/lesson/people-are-dependencies. Accessed 29 November 2026.
Sources
- Resource leveling — Adjusting start and finish dates so that work fits the people and equipment available.
- Dependency (project management) — Links between tasks that come from limited resources rather than from the work itself.
- Float (project management) — Why tasks with float are the first to move when work is rearranged.