Nouns Before Verbs

In one line Break work first into the things to be delivered, then into the tasks that make each one.

There are two ways to begin breaking down a job. One starts with verbs: design, cut, sand, glue, test, deliver. The other starts with nouns: the things that will exist when the work is done. Experienced planners usually start with the nouns. They ask first what will be handed over, and only then what must be done to make each thing.

Take a workshop making a new chair for a café. The nouns are the frame, the seat, the finish, the drawings, the jig that holds the legs at the right angle while the glue sets, and the certificate from the strength test. Under each noun come the verbs: for the seat, choose the timber, cut, shape and sand. A list made only of verbs would include cutting, gluing and finishing, but who would think of the jig or the certificate? They are things, not steps, and no step produces them unless someone names them.

A small website for a clinic works the same way. Its deliverables might be the pages, the booking form, the photographs, the words for each page and a short guide for the receptionist. Lists of activities tend to lose the words and the photographs, because 'build the site' sounds as if it covers them. Naming deliverables first also makes each one checkable: a seat exists and meets its description or it does not, whereas sanding can go on for ever. Earlier in the course, Accepted or Not showed how a finished piece can be checked against criteria agreed in advance.

The cost is that nouns can feel abstract at first, and some people think more naturally in steps. A practical answer is to draft the verbs if that is easier, then ask of each one what thing it makes. Anything the project needs that no verb produces is a gap in the plan.

Go deeper

The PRINCE2 method builds this habit into its planning, which it calls product-based planning. Its first picture, the product breakdown structure, has the same tree shape as a work breakdown but holds only the things to be made. The activities needed to make them come afterwards. Supporters sum up the difference as the first tree saying where you want to go and the second saying how to get there. In practice many teams merge the two, with deliverables at the upper levels and activities at the lowest.

The crates nobody made

Illustration: The crates nobody made

Gani runs a furniture workshop in Jepara, on the north coast of Java. A hotel group ordered two hundred chairs of a new design, to be shipped by sea. His foreman's plan was a list of steps: buy timber, dry it, cut, shape, assemble, sand, finish, inspect. It looked complete, and the foreman was proud of it.

Gani asked a different question: what things will exist when we are done? They listed the chairs, of course, then the approved sample chair, the finishing colours signed off by the hotel, the care leaflet the hotel had asked for, and the packing crates. Nobody's step made crates. The workshop had always sold to local buyers who collected their furniture by truck. Ordering crates three months early cost very little. Finding out in the week of shipping would have cost the contract.

Try this today Look at a to-do list you keep. For each task, write the thing it produces. Is there anything you need that no task makes?

Question 1 of 2

A team in Bishkek, Kyrgyzstan, building a small website for a guesthouse writes its plan as four steps: design, code, test, launch.

Which piece of work is this plan most likely to lose?

Question 2 of 2

The head of a shoe factory in León, Mexico, tells a new planner: 'Before you write down a single task, write down ____.'

Which words best complete her advice?

Cite or share this lesson

A plain reference you can paste into notes or an essay:

Quest2Plan. “Nouns Before Verbs.” https://quest2plan.com/learn/lesson/nouns-before-verbs. Accessed 29 November 2026.

Sources
  • Product breakdown structure — Describes the tree of deliverables used in PRINCE2's product-based planning, and how it differs from a work breakdown.
  • Work breakdown structure — Explains why a breakdown is best organized around outcomes rather than actions.