Nothing Left Out
In one line The 100 per cent rule: the pieces of each branch must add up to all of its work and nothing more.
A breakdown can look neat and still be wrong, because the pieces leave something out. A simple rule checks this. Each set of pieces must add up to exactly the piece above it: all of its work and nothing more. Planners call it the 100 per cent rule, and the project planner Gregory Haugan made it a central principle of his book on work breakdown structures.
The rule works in both directions. Nothing missing: if the pieces under 'renovate the park' are paths, playground, planting and lighting, then the permit, the fencing during works, the removal of the old benches and the notice to neighbours have no home, and work with no home rarely gets done. Nothing extra: a piece outside the agreed scope, such as resurfacing the street beside the park, should not slip in, because the tree then promises work nobody approved. Earlier in the course, Saying What's Out showed why a list of what is out matters.
The rule applies at every level, which is what makes it practical. Walk the tree from the bottom up and at each branch ask: if all these pieces were finished, would the branch above be finished? A family moving house can try it. If the move breaks down into packing, the van and unpacking, the question exposes the gaps: cleaning the old flat, handing back the keys, giving the new address to the bank and the school, saying goodbye to the neighbours.
What plans forget follows a pattern: permissions, the tasks that start and close a job, such as clearing up and handing over, and telling people. These sit between the obvious pieces, so they belong to no one until the check finds them. The rule cannot prove a tree complete, since nobody can list work they have never imagined, but asking the question at every branch, ideally with people who have done similar work, catches much of it.
The market in the park

Hamza, an engineer with the municipality in Meknes, Morocco, had a tidy tree for renovating a small neighbourhood park: new paths, a playground, planting, lighting and a fountain. Before sending it for approval, he walked it from the bottom up with the park's gardener and a woman from the residents' association.
At the fountain branch the gardener asked who would arrange the water connection, which needed its own permit. At the paths branch the resident asked where the Thursday market would go, since its traders set up on the old paths every week. Nobody had thought of the traders, the old benches, or the signs telling people the park was closed. Hamza added a branch called 'before and after the works', with six pieces and an owner for each. The traders moved to the street beside the school for three months, and nobody turned up on a Thursday to find fences.
Try this today Take any plan you have and pick one branch. Ask: if every piece under it were finished, would the branch truly be finished?
Cite or share this lesson
A plain reference you can paste into notes or an essay:
Quest2Plan. “Nothing Left Out.” https://quest2plan.com/learn/lesson/nothing-left-out. Accessed 29 November 2026.
Sources
- Work breakdown structure: the 100% rule — Sets out the rule that the pieces of a breakdown must cover all the work in scope and nothing more.
- Scope (project management) — An overview of what a project's scope is and how it is defined and controlled.