Money for the Unknown
In one line Contingency pays for known risks if they strike; a reserve covers what nobody foresaw. Keep both apart.
Every budget is built from estimates, and estimates are guesses. Some of the ways they can go wrong are already visible: the ground may be harder than the survey says, a supplier may raise prices, a key person may fall ill. Others nobody can name in advance. Sensible projects set money aside for both kinds, and keep the two sums apart.
Contingency is money for known risks: the ones written on the risk list, each with a rough chance and a rough cost. A builder who knows that one site in five on a hillside hits rock adds a sum sized to that risk, and writes down what it is for. The project lead usually controls the contingency and can spend it when one of those risks happens, without asking again. The money is there because the risk was seen in advance.
A reserve is for the surprises nobody foresaw: a new regulation, a flood in the dry season, a supplier going out of business overnight. Because it is not tied to any named risk, it is usually held above the project, by the sponsor or the finance office, and the lead must ask to use it. A hospital refitting a ward might let the project lead draw on contingency for asbestos behind a wall, a known danger in old buildings, while the board keeps a reserve in case the health ministry changes its rules halfway through. Earlier in the course, The Risk Nobody Mentioned showed how naming risks starts this work.
The usual way this goes wrong is that contingency is treated as spare cash. A nicer floor here, an extra feature there, and by the time the risk it was meant for arrives, the money has gone. Contingency that is labelled, tracked and spent on its own risks is still there when it is needed, and what is left can be released once those risks have passed.
Go deeper
Estimators often call the risks contingency covers known unknowns: you can see them, but not whether or when they will strike. Professional cost bodies treat contingency as part of the project's estimate, and keep a management reserve outside it, held by whoever owns the case for the project. Contingency can be sized roughly, as a share of the budget drawn from similar past jobs, or more carefully, by pricing each risk on the list by its chance and its cost and adding the results. Neither is meant to cover a poor estimate, which should be fixed, not cushioned.
Mary Seacole's British Hotel near Balaclava, opened in 1855 to serve soldiers in the Crimean War, shows what a sudden turn does to a venture with no reserve. She and her partner had stocked it for a long war. When peace came in 1856 they were left with goods they could not sell and debts they could not pay, and she was declared bankrupt in London.
The rock under the classrooms

Ximena runs a small building firm in Huancayo, Peru, and has won a contract to add two classrooms to a school on a hillside. Her budget is 380,000 soles, and below the total sit two more lines. The first is a contingency of 30,000 soles, with a note of what it is for: rock under the foundations, likely on this slope, and late delivery of roof steel, which happened on her last two jobs. The second is a reserve of 15,000 soles, held by the school board for anything else.
In the third month the site foreman asks whether the contingency could pay for better windows, since no rock has appeared. Ximena says no: the foundations are not finished, and the risk is still live. Two weeks later the diggers hit rock. Breaking it out costs 22,000 soles, paid from the contingency without a meeting. Once the foundations are done and the roof steel has arrived, she tells the board what is left, and they agree to spend part of it on the windows.
Try this today Look at one plan you are part of and ask: is there money set aside for the risks we know about, and who is allowed to spend it?
Cite or share this lesson
A plain reference you can paste into notes or an essay:
Quest2Plan. “Money for the Unknown.” https://quest2plan.com/learn/lesson/money-for-the-unknown. Accessed 30 November 2026.
Sources
- Cost contingency — What contingency covers, known risks rather than poor estimates, and what it leaves out.
- Cost overrun — How and why projects spend more than planned, and the explanations researchers give.
- Mary Seacole — Her life, the British Hotel near Balaclava and her memoir.