Mixing the Two

In one line Most projects mix the two approaches; the trouble lies at the seams, where a fixed rhythm meets a changing one.

Few real projects are purely one thing. A music festival has a fixed date, a booked site and a safety plan approved by the council months ahead, while its programme of acts, workshops and food stalls can be built and rebuilt in short rounds as bookings come in. A new kitchen appliance needs a factory line tooled months ahead, yet its design can be tried with cooks and changed many times before the tools are cut. Each needs a plan for some parts and learning for others.

The mix is not new. The flight software for the Space Shuttle was written in 17 iterations over 31 months, about eight weeks each, because the programme's requirements kept changing, while the vehicle around it was built to detailed designs. Earlier in the course, Phases and Gates described gates that release money in stages; many hybrids put planned gates around adaptive work inside each phase, much as Boehm's Spiral let risk choose the mix.

The joins are where hybrids hurt. A design team working in two-week rounds may change a part the factory has already tooled for; a festival programme team may book an act whose stage needs more power than the electricians planned. The fixed side complains of churn, the adaptive side of red tape. The usual cures are to agree which decisions must be frozen and by what date, and to put someone from each side in the other's meetings.

Supporters see hybrids as simple realism. Critics warn that a mix can keep the worst of both, the paperwork of the plan and the uncertainty of the experiments, with nobody sure which rules apply. Much depends on whether the people on each side understand the other's rhythm.

A brass band too big for the stage

Illustration: A brass band too big for the stage

Chakib produces a three-day music festival in Essaouira, Morocco. The date, the square, the stage, the security plan and the power supply are fixed by March and approved by the town. The programme is not: his small team adds and drops acts every two weeks as artists confirm, looking at ticket sales and at what the town's hotels report.

In May the programme team books a band with a large brass section and dancers. The stage, planned in February, has no room for them, and the electricians' plan does not cover the extra lights. Chakib does not stop the fortnightly bookings. He sets two rules: any act that needs more stage or power than the fixed plan allows goes to the production manager before it is offered, and the production manager joins every second programme meeting. The band plays a smaller set, and nothing else has to change.

Try this today Find where your work hands over to a team with a different rhythm, and ask what each side needs to know, and by when.

Question 1 of 2

A firm in Penang, Malaysia, is making a new household water filter. Its designers try versions with families every three weeks, but the moulds for the plastic casing take four months to make and cost a great deal.

How should this project be mixed?

Question 2 of 2

On a new metro line in Almaty, Kazakhstan, the stations are built to a fixed plan while the passenger information screens are developed in short rounds. The software team keeps changing the size of the screens.

Where is trouble most likely, and what would help?

Cite or share this lesson

A plain reference you can paste into notes or an essay:

Quest2Plan. “Mixing the Two.” https://quest2plan.com/learn/lesson/mixing-the-two. Accessed 29 November 2026.