Lesson · 6 min Stretch
Lying to Get Started
In one line Some low estimates are not honest mistakes but numbers shaded to win approval, and a project lead may be asked to present one.
Honest optimism is one explanation for low estimates. Bent Flyvbjerg proposed a darker one. In a paper published in 2002 with Mette Skamris Holm and Søren Buhl, titled Underestimating Costs in Public Works Projects: Error or Lie?, he argued that honest errors should fall both ways, some estimates too high and some too low. Instead, across 258 transport projects, they leaned heavily one way, in every kind of project and period studied. The authors concluded that the pattern was best explained by strategic misrepresentation: costs shown low, and benefits high, on purpose, to win approval.
The motive is easy to see. Projects compete for limited money, and the one that looks cheapest and most useful wins. A promoter who gives an honest figure may lose to one who does not. Flyvbjerg calls the result survival of the unfittest: the projects that get built are often the ones whose numbers were shaded most, not the best ones.
The other side deserves a hearing. Early estimates are made before the design is settled, when much is truly unknown and hope fills the gaps; the planning fallacy alone would make errors lean one way. Intent is hard to prove, and many planners resent being called liars. Flyvbjerg himself grants that optimism and deliberate low bidding work together.
Whatever the mix, a project lead may be handed a number to present that they do not believe. Some steps help. Keep the target and the estimate apart, and say which is which. Write down your own range and the assumptions behind it, and give it to those who decide, not only your manager. Show the record of similar projects. Do not sign a figure you know to be false. The larger cure lies with funders: outside review and the outside view taught in Look at Projects Like Yours.
Forty million, or the truth

Damaris leads the project to build a covered market hall for a county government in Kisumu, Kenya. Her estimate, built from three similar halls in the region, is 55 to 65 million shillings. Her director tells her to present 40 million to the county assembly, because a higher figure will not be approved this year.
Damaris prepares two pages. The first shows the director's 40 million as a funding limit and lists what the hall could include for that amount: fewer stalls, no cold store, a simpler roof. The second shows her estimate for the full design, with the costs of the three earlier halls beside it. She shows both pages to her director before the meeting and says she will not present 40 million as the cost of the full hall. After an uneasy hour he agrees. The assembly approves a smaller first phase at 40 million, with the cold store to follow.
Try this today Next time you give an estimate, write down the range you believe beside the number you were hoping to give.
Cite or share this lesson
A plain reference you can paste into notes or an essay:
Quest2Plan. “Lying to Get Started.” https://quest2plan.com/learn/lesson/lying-to-get-started. Accessed 29 November 2026.
Sources
- Underestimating Costs in Public Works Projects: Error or Lie? — Flyvbjerg, Skamris Holm and Buhl's study of 258 transport projects.
- Bent Flyvbjerg — The researcher's career, books and fields of study.