How Likely, How Bad?
In one line Rating risks for likelihood and impact shows which come first, but the grid can hide rare disasters.
A register fills quickly, and a team cannot act on forty risks at once. The common way to sort them is to give each two ratings: how likely it is to happen, and how much harm it would do if it did. Each is scored on a short scale, often one to five, and the two are multiplied or plotted on a grid, with likelihood along one side and impact along the other. Risks in the top corner, likely and damaging, are dealt with first; those in the bottom corner are watched or left alone.
The grid is popular because it is quick, it can be filled in at a meeting, and it turns a long list into a picture anyone can read. A haulage firm planning a new freight route across mountains might rate a lorry breakdown as likely but minor, a closed border crossing as unlikely but serious, and a landslide on the pass as rare but severe. The ratings start a conversation about which risks deserve money and attention.
Its weakness is that it squeezes very different risks into the same few boxes. A road closed for a day and a bridge collapse that shuts the route for a year can end up with similar scores if one is rated likely and minor and the other rare and catastrophic: three times two and one times five are not far apart. Teams also drift towards the middle of every scale, and a grid full of medium risks says little. For the rare, severe ones, look past the score and ask what would happen if this came true, and whether the project could survive it.
Earlier in the course, Three Numbers Are Better Than One showed that a single number hides a range. A risk score does the same, and its ratings are judgements, not measurements, so they are best argued over in the open.
Go deeper
In a 2008 paper, 'What's Wrong with Risk Matrices?', the risk analyst Tony Cox argued that grids can give the same rating to risks that differ greatly in size, and can even rank a smaller risk above a larger one. Later researchers found that rankings can change when the same risks are put on a grid with different scales. Defenders reply that the grid was never meant as a measurement, only a quick way to start a discussion, and that for most projects this is enough. Where the stakes are high, many analysts suggest estimating the chances and costs in numbers instead.
The Indian engineer M. Visvesvaraya, planning flood protection for Hyderabad after the Musi flood of 1908, faced a risk at the far corner of the grid: rare, but able to kill thousands. His reservoirs above the city were meant to hold back a flood on that scale, not an ordinary year's.
Melons and the border

Akmal and his brothers farm cotton near Jizzakh, Uzbekistan, and plan to turn twenty hectares over to melons for export. Over tea they score four risks from one to five. A late frost: likelihood 2, impact 3, score 6. Pests: 4 and 2, score 8. The buyer pulling out: 2 and 4, score 8. A border closure while loaded lorries wait: 1 and 5, score 5. On the grid, the border sits lowest of all.
Akmal then asks a different question of each: what would it actually do to us? Pests would cost part of a crop. A frost would cost a few weeks. But a closure at harvest, with the whole crop on the road and the seed bought on a loan, could cost them the season and possibly the farm. They keep the grid for the everyday risks and give the border its own plan. They agree with a market in Tashkent to take part of the crop if needed, and stagger the planting so the melons ripen over six weeks rather than two.
Try this today Take three risks from any plan and score each from 1 to 5 for chance and for damage. Which would you look at first, and why?
Cite or share this lesson
A plain reference you can paste into notes or an essay:
Quest2Plan. “How Likely, How Bad?.” https://quest2plan.com/learn/lesson/how-likely-how-bad. Accessed 29 November 2026.
Sources
- Risk matrix — The likelihood and severity grid, its history and the main criticisms, including Cox's 2008 paper.
- Risk assessment — How hazards, their likelihood and their consequences are identified and judged.
- M. Visvesvaraya — The Indian engineer, his floodgates, dams and flood works.