Four Values From a Ski Lodge

In one line The agile manifesto prizes people, working results, collaboration and change, while still valuing plans and documents.

From 11 to 13 February 2001, seventeen people met at The Lodge at Snowbird, a ski resort in the Wasatch mountains of Utah. They came from rival camps that had been building software in lighter ways: Extreme Programming, whose founder Kent Beck was there; Scrum, represented by Ken Schwaber and Jeff Sutherland; and others such as DSDM and Crystal. Most disliked being called 'lightweight' and chose the word agile instead. What they could all agree on fits on one page, the Manifesto for Agile Software Development.

Its heart is four pairs. In the authors' words they came to value 'Individuals and interactions over processes and tools', 'Working software over comprehensive documentation', 'Customer collaboration over contract negotiation' and 'Responding to change over following a plan'. Put plainly: people talking solve more than any procedure; a piece that works shows progress where a document can only promise it; working with the customer beats arguing over clauses; and a plan is a best guess, to be updated when the world moves.

The sentence that follows is often forgotten: 'while there is value in the items on the right, we value the items on the left more.' The manifesto does not reject plans, tools, contracts or documents. It ranks them. Twelve principles add detail, among them delivering working software frequently, every couple of weeks to every couple of months, the sooner the better, business people and developers working together daily, and a pace the team could keep up indefinitely.

Short words travel far and can be misread. Some teams took the four lines as permission to plan nothing and write nothing down, which the authors did not mean; others hung them on the wall and changed nothing. The values say what to prefer when two good things pull apart, not what to do on Monday.

The seat map

Illustration: The seat map

Lindani leads a team of five in Durban, South Africa, writing a booking system for a coach company. The contract runs to sixty pages, and every change the company asks for needs a signed change request and a new price. Three months in, the company's head of bookings asks for passengers to choose their seats on a map, and the two sides spend a fortnight arguing over whether the contract covers it.

Lindani proposes a different rhythm. Every two weeks the team will show the head of bookings a working piece of the system, she will say what matters next, and changes inside the agreed budget will need no paperwork. He keeps two things from the old way: a short written note of each decision, and a manual for the staff who will look after the system. The seat map arrives in the fourth fortnight, and the clerks are using the first screens well before the contract's final date.

Try this today Pick one meeting, form or document you use. Ask which side of the manifesto's four pairs it serves, and whether it earns its place.

Question 1 of 2

A project office in Amman, Jordan, requires every team to log each question in a tracking tool and wait for an answer there, even when the two people involved sit at neighbouring desks.

Which of the four pairs is this office turning upside down?

Question 2 of 2

Kasim, a new team lead in Cairo, announces that since his team is now agile it will write no documents at all, not even notes for the people who will maintain the system.

How would the manifesto's authors most likely answer him?