
Lesson · 6 min Gentle
Avoid, Reduce, Share, Accept
In one line Each risk gets one of four responses: change the plan to avoid it, reduce it, share it, or accept it knowingly.
Once a risk is rated and owned, someone has to decide what to do about it. The choices fall into four broad kinds, and naming them helps a team see options it might otherwise miss.
Avoid it, by changing the plan so the risk no longer applies: build the house on the higher part of the plot, away from the stream that floods, or hold the conference in a city most speakers can enter without a visa. Reduce it, by making it less likely or less harmful: test the soil before pouring the foundations, or line up a stand-in for the opening speaker. Share it with someone better placed to carry it: insure the building materials against theft, or agree a contract under which the venue pays if the hall is not ready. Accept it, deciding knowingly to bear it if it happens, often with a fallback and a little money ready.
Each response has a cost. Avoiding may mean a dearer plot or a less appealing city. Reducing costs time and money now for a danger that may never arrive. Sharing costs a premium or a higher price, and the other party carries only what the contract says, so a delay can still hurt the project after the money comes back. The right choice weighs that cost against how likely and how bad the risk is, which is why the ratings matter.
Accepting a risk is a decision, not a failure to decide. A family building a house may accept that a wet month will slow the roofers, because covering the site would cost more than the delay. That is different from never thinking about it. Written down, with the reason and a fallback, acceptance is a choice the team can revisit; left unspoken, it is luck. Earlier in the course, Money for the Unknown showed contingency set aside for accepted risks like these.
Go deeper
The Indian engineer M. Visvesvaraya used several of these at once in Hyderabad after the Musi flood of 1908. Reservoirs upstream reduced the flood that could reach the city, and drainage within it reduced the harm heavy rain could do. The river itself could not be removed, so the risk that remained had to be accepted and watched.
Four risks, four answers

Carmen is organizing a three-day regional conference on midwifery training in Kigali, Rwanda, for four hundred delegates from twelve countries. Her four biggest risks get four different answers. Speakers' visas may be late, so she reduces the risk by sending invitation letters four months early. The main hall's air conditioning may fail, so she shares it: the venue's contract obliges it to provide a second hall at its own cost. The hotel she first chose sits beside a building site, so she avoids that risk by booking another. A strike at one regional airline could strand some delegates; she accepts it, keeps a list of other routes and sets aside a small sum to rebook.
At the committee meeting a member asks why the strike is not insured. Carmen has priced it: cover would cost more than rebooking the twenty delegates who use that airline. She writes the reason in the register beside the word 'accept'. In the end two visas still arrive late, and those speakers give their talks by video link.
Try this today Pick one risk in your week. Write what avoiding, reducing, sharing and accepting it would each look like, then choose.
Cite or share this lesson
A plain reference you can paste into notes or an essay:
Quest2Plan. “Avoid, Reduce, Share, Accept.” https://quest2plan.com/learn/lesson/four-responses. Accessed 29 November 2026.
Sources
- Risk management: potential risk treatments — Avoidance, reduction, sharing and retention of risk, with examples of each.
- Insurance — The commonest way of sharing a risk: moving the cost of a possible loss to an insurer for a premium.
- M. Visvesvaraya — The Indian engineer, his floodgates, dams and flood works.