Fast, Cheap, Good: Pick Two?

In one line The pick-two slogan is a fair warning but not a law: waste can be cut for free, and buying speed can backfire.

'Fast, cheap, good: pick two.' The slogan hangs on the walls of print shops and repair garages around the world, and it is a fair warning. A customer who wants the job tomorrow, at a low price and done well, is usually asking for one more thing than the work can give. The saying makes the triangle of trades feel real in five words.

But the slogan is too simple in three ways. First, some changes cost nothing. A clearer brief, fewer hand-overs or a decision made on Monday instead of Friday can make work faster and better at no extra price; removing waste is not a trade. Second, trades are not straight lines. Spending twice as much rarely buys twice the speed; past a point, each extra unit of money buys less.

Third, the most tempting way to buy speed can slow a project down. Fred Brooks, who managed a very large computer programming project in the 1960s, wrote in The Mythical Man-Month (1975) that adding people to a late software project makes it later. The newcomers need teaching, usually by the people who were doing the work, and every extra person adds more conversations to keep in step. Money spent on people is not speed bought unless the work splits cleanly.

So the slogan helps as a warning and misleads as a law. Before accepting that one of the three must suffer, it is worth asking whether something can be removed instead, and whether the speed you are paying for will truly arrive.

Go deeper

Brooks gave two reasons. Newcomers take time to become useful, and someone already on the project has to teach them. And the lines of communication grow faster than the team: three people make three pairs who must keep in step, while ten people make forty-five. The rule bends where tasks can be split cleanly. Many hands do speed a harvest or a wall of sandbags, because each worker needs little from the others.

Frugal design is another way the slogan bends. Fe del Mundo, a Filipino paediatrician, devised a bamboo incubator for villages without electricity: cheap and simple to make, and good in the way that mattered there, though it would never pass for a hospital machine. Deciding what good means can free both money and time.

The programme that was late

Illustration: The programme that was late

Dian is organizing a three-day book fair in the Indonesian city of Bandung, and the printed programme is late. The printer says he can rush it for double the price, or do it properly in a week, after the fair has opened. Fast and good would be dear; cheap and good would be slow. The slogan seems to fit exactly.

Then Dian looks at why the programme is late. The text has been passed between four volunteers for sign-off, each changing a few words and sending it back. She asks one person to make the last decisions in a single afternoon, cuts the hand-overs, and sends the file to the printer two days earlier than anyone expected. The programme comes out on time, at the normal price, and with fewer errors than the last draft. Nothing was traded. The delay had been waste, not a law.

Try this today Find one delay in your work this week. Ask whether fixing it would cost money, or whether it is simply waste that could go.

Question 1 of 2

A team in Nairobi, Kenya, building a payroll system for a farmers' cooperative is a month behind. The manager plans to hire six new programmers next week to catch up.

What risk does this plan run?

Question 2 of 2

A caterer preparing a conference lunch in Beirut, Lebanon, sets up one prep table for each dish, so cooks stop crossing the kitchen. The lunch is ready an hour sooner.

What does this change show about the pick-two slogan?

Cite or share this lesson

A plain reference you can paste into notes or an essay:

Quest2Plan. “Fast, Cheap, Good: Pick Two?.” https://quest2plan.com/learn/lesson/fast-cheap-good. Accessed 29 November 2026.

Sources
  • Brooks's law — Fred Brooks's observation that adding people to a late software project makes it later, and its limits.
  • Project management triangle — Includes the 'good, fast, cheap: choose two' saying and how it relates to the triangle.
  • Fe del Mundo — The Filipino paediatrician, her hospital and her bamboo incubator.