Earned Value in Plain Words

In one line Earned value compares work planned, work done and its cost, to show both lateness and overspending.

Comparing spending with a baseline has a blind spot: spending on plan tells you nothing about whether the work is on plan. Earned value fills that gap by asking three questions, each answered in money. How much work did we plan to have finished by now? How much have we actually finished? And what did that finished work cost?

Take a job to build ten identical houses at 50,000 each, half a million in all, planned at one house a month. At the end of month four the plan said four houses, so the planned value is 200,000. Only three are finished, so the earned value is three houses at their budgeted price: 150,000. The bills so far come to 180,000, the actual cost. Earned value against planned value shows the job is behind, a month's work short. Earned value against actual cost shows it is overspending: 180,000 paid for 150,000 worth of houses.

The idea grew up in American defence projects in the 1960s, when the Department of Defense wanted contractors on large programmes to report progress in a common way; in 1967 it set out criteria that their cost and schedule systems had to meet. It has since spread to public works, building and many other fields, in lighter and heavier forms.

Its strength is that it pulls apart two problems that usually hide each other. Its weakness is the earned value itself, which depends on an honest measure of what is done. A task reported as '90 per cent complete' for weeks earns value it has not truly earned. Many teams count a piece of work as earned only when it is finished, or give half at the start and half at the end, which is cruder but harder to fool.

Go deeper

Practitioners turn the two comparisons into ratios. Earned value divided by actual cost is the cost performance index: below 1, each unit of money is buying less work than planned. Earned value divided by planned value is the schedule performance index: below 1, the work is behind. For the houses these are 150,000 over 180,000, about 0.83, and 150,000 over 200,000, which is 0.75. A common rough forecast divides the whole budget by the cost index to estimate the final cost: here about 600,000 instead of 500,000. Such forecasts assume the past pace continues, which is a guess, not a promise.

Twelve roofs and a spending report

Illustration: Twelve roofs and a spending report

Xolani, a captain in an army engineering unit near Bloemfontein, South Africa, oversees the re-roofing of twelve barracks blocks, budgeted at 80,000 rand each and planned at two a week. At the end of week three the report says 'spending on track': 480,000 rand spent, exactly as the plan expected.

Xolani asks for the earned value. Six roofs were planned by now, so the planned value is 480,000 rand. Only four are finished, so the earned value is 320,000. Spending matches the plan, but the job is two roofs behind, and it has paid 480,000 rand for 320,000 worth of work, so each rand is buying about two thirds of what it should. The unit is late and overspending at once, and the spending report hid both. He takes the figures to his commanding officer with the cause, a crew short of qualified roofers, and asks for two more.

Try this today Pick a task list you are working through. Count what you planned to finish by today and what is truly finished, not nearly.

Question 1 of 2

A clinic-building project in Ndola, Zambia, reports a planned value of 300,000, an earned value of 300,000 and an actual cost of 360,000.

What do these figures say about the project?

Question 2 of 2

Timur, a site engineer on a road contract near Bukhara, Uzbekistan, reports a bridge section as '90 per cent complete'. It has been reported that way for five weeks.

Why does this matter for an earned value report?

Cite or share this lesson

A plain reference you can paste into notes or an essay:

Quest2Plan. “Earned Value in Plain Words.” https://quest2plan.com/learn/lesson/earned-value-plainly. Accessed 29 November 2026.

Sources