DuPont's Critical Path
In one line The critical path was born in plant shutdowns, where jobs were familiar, their order fixed and every lost day priced.
Every so often a chemical plant must stop for maintenance. Vessels are drained and cleaned, pumps rebuilt, pipes replaced, and nothing is made until the last valve is back. Each day of shutdown costs lost output, and the work has a strict order: a tank cannot be inspected until it has been emptied and made safe. In the mid-1950s the chemical firm DuPont wanted a better way to plan such jobs, and its building projects too.
In 1956 and 1957 Morgan Walker of DuPont worked with James Kelley of Remington Rand, the company that made the UNIVAC computer. Their method, set out in a 1959 paper, is the one met earlier in The Critical Path: list the jobs, record what each waits for, give each a duration, and find the longest chain. They also aimed at the lowest overall cost. Many jobs can be shortened by spending more, on overtime or an extra crew, so the method looked for the cheapest days to buy back on the critical chain, and stopped where a shorter shutdown would cost more than it saved.
Shutdowns made a good test. The jobs were familiar, so their lengths could be estimated from past years, unlike the new missile work PERT faced. Their order was fixed by safety and by the plant itself. And the price of an extra day was easy to put in money. The sums were heavy for hundreds of jobs, so they ran on a UNIVAC I, a machine of more than six thousand vacuum tubes that filled a room and held about a thousand words in its memory.
Today a laptop does the same sums in a moment, and the method has spread far beyond chemical plants. Its origin still marks its strengths: it works best where the jobs are known and their order is firm, and least well where nobody can say how long the work will take.
Buying back days at the plant

Rehana plans the yearly shutdown at a fertilizer plant near Aqaba, in Jordan. For years each foreman had planned his own jobs, and the plant had restarted two or three days after its ten-day target. This time she listed all 140 jobs, what each waited for, and how long each had taken in the last three shutdowns. The longest chain ran through the acid tank: draining, cleaning, inspecting its lining, repairs and refilling, eleven days in all.
The plant manager offered overtime money. Rehana priced each way of shortening a job on that chain against a day of lost output. A second cleaning crew cut a day for a fraction of a day's output, and a night shift on the lining repairs cut another for about half. Shortening the inspection meant flying in a specialist at more than a day's worth, so she stopped there. The pump overhauls looked busy but had three days to spare, and got no overtime. The plant restarted on day nine.
Try this today Think of a job you repeat each year, such as a move, a festival or a stocktake. Could you list its steps, their order and their usual lengths from memory?
Cite or share this lesson
A plain reference you can paste into notes or an essay:
Quest2Plan. “DuPont's Critical Path.” https://quest2plan.com/learn/lesson/duponts-critical-path. Accessed 29 November 2026.
Sources
- Network logic was aided by mainframe power — How DuPont and Remington Rand's Kelley and Walker used a UNIVAC I to lay the basis of the critical path method.
- The Origins of CPM, PDM and PERT Schedules — A short history: maintenance shutdowns at DuPont's works and the 1959 paper by Kelley and Walker.
- UNIVAC I — The room-sized computer of the 1950s: its vacuum tubes, memory and speed.