Critical Chain

In one line Cut the hidden padding from tasks, pool the safety in a buffer at the end, and watch how fast it is used.

In 1997 Goldratt turned from factories to projects, with another novel, Critical Chain. His question was why projects run late even when every task estimate contains safety. He pointed to two habits. People who know they have time to spare tend to start late, which he called the student syndrome, and work tends to fill the time allowed, as C. Northcote Parkinson had joked in 1955. So padding gets used whether needed or not, and early finishes are rarely passed on.

Earlier in the course, Why Hidden Padding Fails gave the remedy in outline; critical chain is the full method. Each task is estimated at a time it has about an even chance of meeting, with the private padding taken out. The safety is gathered into a project buffer at the end of the longest chain of dependent tasks, with smaller feeding buffers where side paths join it. The chain takes people into account as well as tasks: if one surveyor is needed for two jobs, they cannot run side by side, which is why Goldratt spoke of a chain rather than a path.

Then the team watches the buffer. A simple chart compares how much of the buffer has been used with how much of the chain is complete. A third of the buffer gone at the halfway mark is fine; most of it gone by then is the signal to act.

There are fair doubts. Willy Herroelen and Roel Leus reported in 2001 that the common rule of making the buffer half the length of the chain can over-protect large projects, and that keeping the first schedule rather than updating it can lengthen them. Reviewers of Goldratt's wider theory have said its benefits are not well shown in research. And the method needs trust: if people are blamed for missing estimates meant to be missed half the time, the padding comes back.

One buffer for the new wing

Illustration: One buffer for the new wing

Madina manages the building of a new maternity wing for a hospital in Shymkent, Kazakhstan. The contractors' schedule runs to fourteen months, and every task in it carries its owner's own margin. In the first three months, she notices, not a single task finished early, though several started late.

With the contractors she rebuilds the plan. Each foreman gives a time he has an even chance of meeting, and the margins taken out are pooled: about ten months of chained tasks, then a four-month buffer before the opening date, which stays where it was. Because the same crane crew is needed for the roof and the lift shaft, those two jobs are put in line, not side by side. Each Monday she marks the chart. By the sixth month the chain is more than half done and a quarter of the buffer is gone. When a late steel delivery eats six weeks at once, more than half the buffer is gone with the chain only a little past halfway; the chart shows it is time to act, and the steel for the next phase is ordered early.

Try this today For your next task, write the time it needs if nothing goes wrong and the time with safety. Keep the gap as a separate reserve.

Question 1 of 2

Octavio is planning the fit-out of a clinic in Cali, Colombia. Each of his eight trades has quietly added a week of safety to its own task.

What would the critical chain approach do with those eight weeks?

Question 2 of 2

Naima tracks a museum renovation in Meknes, Morocco, against its buffer. Her weekly note reads: 'Chain 30 per cent complete; buffer used: ____. Time to act.'

Which entry would justify her last three words?

Cite or share this lesson

A plain reference you can paste into notes or an essay:

Quest2Plan. “Critical Chain.” https://quest2plan.com/learn/lesson/critical-chain. Accessed 29 November 2026.

Sources
  • Critical chain project management — Even-odds task estimates, project and feeding buffers, and the chart of buffer use against progress.
  • Student syndrome — Goldratt's name, in Critical Chain, for starting work only when the deadline looms.
  • Parkinson's law — C. Northcote Parkinson's essay of 1955: work expands to fill the time available.