Choosing Among Projects

In one line Portfolio management looks at every project at once and decides which to start, which to keep and which to stop.

Every organization has more good ideas than people and money. Portfolio management looks at all its projects together, those proposed and those already running, and decides which to start, which to continue and which to stop. The word comes from finance: in 1952 the economist Harry Markowitz argued that an investor should judge each holding by how it fits the whole set, not only on its own merits. Projects work the same way. Two safe projects that both depend on one scarce engineer are riskier together than either looks alone.

Many organizations score proposals: how well each serves the strategy, its benefits against its cost, its risk and how soon it pays back. A score lets a board set unlike things, a new clinic and a new payroll system, side by side. Then the board balances the set: some quick wins and some long bets, some upkeep and some growth, and no more work than its people can carry. Earlier in the course, The Business Case showed how a single proposal is weighed; the portfolio weighs proposals against each other.

Scores need care. Weights can be adjusted until the favourite comes top, and a figure such as 'strategic fit: 4 out of 5' is a judgement dressed as a number. Many boards use scores to sort the list and start the argument, and then decide by talking.

The hardest part is not choosing what to start but agreeing what to stop. Every running project has a sponsor, a team and money already spent, and stopping it can feel like admitting a mistake. Yet a portfolio that only ever adds fills up until nothing moves. A good review asks of each running project the question asked of new ones, and treats money already spent as gone, as Letting a Project End explained.

Go deeper

Fazle Hasan Abed, who founded BRAC in Bangladesh in 1972, made choosing a discipline. BRAC tried ideas on a small scale, checked what had really changed, and spread what worked, while dropping or reshaping what did not. He argued that a problem the size of a country needed programmes big enough to match it, and that being small and admired was not enough.

Nine proposals, money for four

Illustration: Nine proposals, money for four

Mekdes is director of programmes at a water charity in Mekelle, Ethiopia. This year nine proposals compete for money enough for four. Her team scores each one for how many people would gain clean water, cost per person, risk and fit with the charity's plan to focus on schools. A well-repair scheme and two school latrine projects come top, and a fourth place goes, after argument, to a riskier rainwater pilot, so the charity keeps learning something new.

Then Mekdes puts the charity's six running projects through the same scoring. One, a drilling project in hard rock, has used most of its budget and found water in only two of eight holes. Its manager wants another year. Mekdes asks the board whether, knowing what they know now, they would fund it today. After a long meeting they agree to stop it, move its drilling team to the well repairs and write up what the failed holes taught them.

Try this today List everything your team has started and not finished. For each, ask: knowing what we know now, would we start this today?

Question 1 of 2

Marwan runs the planning office of a logistics company in Beirut. The board's favourite proposal, a new warehouse, came fifth in this year's scoring. The weights were then changed three times, and it now comes first.

What is the main concern here?

Question 2 of 2

Kalsoom is setting up an annual portfolio review for a development charity in Lahore. Its steps are: (1) score each proposal and running project; (2) gather every proposal and every running project into one list; (3) balance the set against the people and money available; (4) decide and announce what starts, continues and stops.

Which order makes most sense?

Cite or share this lesson

A plain reference you can paste into notes or an essay:

Quest2Plan. “Choosing Among Projects.” https://quest2plan.com/learn/lesson/choosing-among-projects. Accessed 29 November 2026.

Sources
  • Project portfolio management — Managing projects as a set, aligning them with strategy and limited resources, and the idea's roots in 1950s finance.
  • Harry Markowitz — The economist whose 1952 paper 'Portfolio Selection' founded the idea of judging investments as a set.
  • Fazle Hasan Abed — The founder of BRAC and how it grew its programmes.