Breaking It Down Together
In one line A breakdown made by the people who will do the work finds more of it and finds owners for its pieces.
No single person knows all the work in a project. The lighting technician knows about the cables; the parent who runs the costume cupboard knows the costumes must be washed after the dress rehearsal. A breakdown drawn alone holds what its author knows. A breakdown drawn by the people who will do the work holds much more.
A common way to do it uses sticky notes on a wall. Write the finished result at the top. Each person writes pieces of work, one per note, in silence for ten minutes, so that the loudest voices do not set the list. Then the notes go on the wall and the group sorts them into clusters under the main deliverables, merging duplicates and naming gaps. The sorting resembles the affinity diagram, which Jiro Kawakita devised in Japan in the 1960s. Last, the group walks the tree and asks of each branch whether anything is missing.
Two other things happen in such a session. People see the whole job, including the parts that depend on them. And pieces find owners as they are named: the person who wrote 'borrow chairs' is often the person best placed to do it, and saying so in front of the group is a public promise. Earlier in the course, Plans Made With the Team described why people tend to believe in plans they helped to make, and Too Many Cooks why each piece needs one named owner.
There are costs. A session takes an hour or two of everyone's time, a strong lead can still dominate it, and a large group can drown in notes. Keeping to the people who do the work, writing silently before talking, and asking one person to tidy the tree afterwards all help. Some leads prefer to draft a tree and ask the team to correct it, which is quicker but tends to find less.
Go deeper
The Colombian sociologist Orlando Fals Borda built a research method on the same belief. In participatory action research, the people affected by a problem take part in studying it, from choosing the questions to deciding what the findings mean, because they know parts of it no outsider can see.
Ninety-four notes for a school play

Githinji, a teacher at a secondary school in Eldoret, Kenya, had directed the school play for three years and planned it alone each time. This year he invited twelve people for an hour after classes: students, two parents, the caretaker and the music teacher. At the top of a classroom wall he wrote: three evenings of the play, full house.
In ten silent minutes they wrote ninety-four notes. Sorted under the script, the cast, the set, costumes, music, the hall and the audience, they showed work Githinji had never planned: returning the chairs borrowed from the church next door, keeping the fire exits clear for the inspection, a ramp for a grandmother who used a wheelchair. As each cluster formed, people claimed pieces. The caretaker took the chairs and the exits, since he knew both. Githinji left with a tree twice the size of his old plans, and most of its pieces already had a name on them.
Try this today Before your next plan, ask two people who will do the work to write down, separately, everything they think it involves. Compare the lists.
Cite or share this lesson
A plain reference you can paste into notes or an essay:
Quest2Plan. “Breaking It Down Together.” https://quest2plan.com/learn/lesson/breaking-it-down-together. Accessed 29 November 2026.
Sources
- Affinity diagram — Describes the method of sorting ideas on cards into related groups, devised by Jiro Kawakita.
- Nominal group technique — A structured group method in which members first write ideas down silently before discussing them.
- Orlando Fals Borda — The Colombian sociologist and participatory action research.