Boehm's Spiral

In one line In Boehm's spiral each loop finds the biggest risk, reduces it with a prototype or study, then plans the next loop.

In 1986 Barry Boehm, then chief scientist of the defence systems group of a large American engineering firm, described a way out of the argument between planning and learning. His paper, A Spiral Model of Software Development and Enhancement, appeared in a newsletter for software engineers, and a version in the magazine Computer in 1988 reached a far wider audience.

The spiral pictures a project as a series of loops, each wider than the last as more money is spent. Each loop does four things. It sets the objectives for this round, the other ways of meeting them and the limits; it weighs those options and finds the biggest risk; it reduces that risk with a prototype, a simulation or a study, and builds and checks the next piece; and it reviews the results and plans the next loop. A project might spend its first loops on cheap studies and its last on building to a detailed design.

The key is that risk decides how much of each approach to use. Where the danger is that users will reject the result, a loop builds a prototype for them to try. Where the danger is that costly parts will not fit together, a loop writes a precise specification. Boehm later called the spiral a process model generator: a step-by-step plan and a run of experiments can each be what it produces, when the risks point that way. Earlier in the course, The Cone of Uncertainty showed estimates narrowing as questions are answered; each loop answers the most dangerous question first.

Boehm warned that his famous diagram misled people. The spiral is not a string of small waterfalls, and its steps need not follow the order drawn. It also asks a lot of whoever judges the risks, since loops spent on the wrong question are wasted, and it sits awkwardly with contracts that fix a full specification at the start.

Go deeper

Boehm kept refining the spiral. In a report from a workshop held in 2000 he compared it to stud poker, where a player puts in a little money, sees more cards and then decides whether to stay in: each loop buys information before a bigger stake. He also added three fixed milestones, so that the loops could not drift on for ever: agreement on the system's objectives, an architecture shown to be workable, and a first version that people can actually use.

Three loops at the coast

Illustration: Three loops at the coast

Cristian leads a project at a naval base in Talcahuano, Chile, to send pictures from the coastal radars to the displays on patrol ships. In the first loop his team asks what could sink the project. The answer is not the screens but the radio link: nobody knows whether it can carry radar pictures fast enough in heavy weather. So the first loop spends six weeks and a small budget on a test rig on the cliffs, not on design documents.

The rig shows the link works, but only if the pictures are simplified. In the second loop the biggest risk becomes the officers: will they trust a simplified picture? A rough version of the display goes to two ship crews for a month at sea. Only in the third loop, with both risks reduced, does Cristian's team write a full specification and agree a fixed price with the navy for building the rest.

Try this today Ask of your current work: what is the one thing most likely to sink it, and what is the cheapest way to find out?

Question 1 of 2

In one loop of a spiral for a flood-warning system in Hue, Vietnam, the steps are: (1) build and test a prototype of the river sensors; (2) agree with the province what this round must achieve; (3) review the results and plan the next loop; (4) find that the riskiest question is whether the sensors survive a flood.

In what order would these steps come within the loop?

Question 2 of 2

Baurzhan's team in Astana, Kazakhstan, is building a grain-tracking system for a farmers' cooperative. Its biggest risk is that members will not bother to use it on their farms.

What would the next loop of Boehm's spiral most likely do?