Accepted or Not

In one line Acceptance criteria say, before work starts, what the customer will check before calling a piece of work finished.

At the end of many projects there is a familiar argument. The builder says the job is done; the customer walks round and says it is not. Neither is lying. They are judging against different pictures in their heads, and the pictures were never put side by side. Acceptance criteria are the cure: a short list, agreed before the work starts, of what the customer will check before calling a piece of work finished.

Good criteria are written in terms the customer can test without being an expert. For a garden wall: one metre twenty high along its length; no gap a hand can pass through; the old rose bed left untouched; rubble taken away. For an online booking form: a person can book a table for up to eight people in under two minutes on a phone; a confirmation arrives by text; a booking for a full evening is refused politely, with other times offered. Each line can be answered yes or no.

The value lies in the timing. Agreed early, criteria shape the work: the builder knows the rose bed matters before the digger arrives. They also turn an end-of-project quarrel into a check. If every line passes, the work is accepted, even if the customer now wishes for something more; that wish is a new request, not a failure. Earlier in the course, Goals You Can Check made the whole project's aim checkable; acceptance criteria do the same for each thing it hands over.

Criteria have limits. A list cannot capture everything a customer cares about, and a team can meet every line and still hand over something nobody likes. Some teams write the criteria with users and revise them as both sides learn; others fix them in a contract. The first keeps the work close to what people need, and the second guards both parties where there is little trust.

Six lines on the back of a quote

Illustration: Six lines on the back of a quote

Ozan is a builder near Bursa, in Turkey. Last year a terrace job ended badly: the owner disliked the colour of the mortar and said the old fig tree had been damaged, and Ozan waited months to be paid. So when a retired teacher asked him to rebuild the stone wall along her terrace, he sat with her before giving a price and wrote five lines on the back of the quote.

The wall follows the old line. It reaches the mark on the gatepost. The old stone faces the street. There are drainage holes every two metres so rain does not pool. The terrace is swept and the rubble gone. She read them and added a sixth: the roots of her olive tree are not cut. Ozan priced in two days of digging by hand around them. On the last day they walked the list together and every line passed. She then asked for a stone bench built into the wall. Ozan wrote it up as a new small job, with its own price.

Try this today Before your next handover, write three things the person receiving it will check. Show them the list and ask what is missing.

Question 1 of 2

Nomvula's team in Durban, South Africa, is building an online booking form for a clinic. The clinic manager says she will accept it 'when it works well'.

Which criterion would help the team most?

Question 2 of 2

A team in Cusco, Peru, restores the roof of a community hall. At the handover, the committee refuses to sign off because the gutters were not replaced, though nobody had mentioned gutters before.

What would most likely have prevented this dispute?

Cite or share this lesson

A plain reference you can paste into notes or an essay:

Quest2Plan. “Accepted or Not.” https://quest2plan.com/learn/lesson/accepted-or-not. Accessed 29 November 2026.

Sources
  • Acceptance testing — How users and customers check work against agreed criteria before accepting it.
  • Requirement — What makes a requirement clear and testable, and common ways requirements go wrong.