Critical path: the one-page template

The headings from the Critical path card, with room to write under each. Print it, or save it as a PDF and fill it in on screen.

Every template

Planning

Critical path

The longest chain of dependent tasks in a plan, which sets the shortest time the whole project can take and shows where delay hurts most.

  1. Task
  2. Duration
  3. Waits for
  4. Earliest start and finish
  5. Latest start and finish
  6. Float
  7. On the critical path? (yes or no)
  8. Who watches it

How to use it: quest2plan.com/learn/ideas/toolkit/critical-path